FLOW CONTROL DURING THE RIVER DIVERSION BY MEANS OF A PLANNED SEQUENCE IN THE OPERATION OF THE SPILLWAY COFFERDAMS

机译:溢洪道作业中利用预定顺序进行河流分流的流量控制。

获取原文
获取原文并翻译 | 示例

摘要

The project of Pichi Picun Leufu in the argentinian Patagonia was conceived a long time ago with little concern about environmental impact as was the trend in those days. The third stage of the river diversion process was thought counting on a complete closure of the river flow through a period of time up to 18 hours during which the reservoir increased its elevation in 10 meters for the water to resume flowing through the spillway crests. In such a long closure, the river would have diminished so bad its water contents that a damage could have been produced to the fish population. By means of a detailed study of the reservoir filling process and a very precise hydraulic operations with the spillway cofferdams, the flow was thoroughly controlled to reduce the closure time to 2 hours and a half avoiding, in this way, any damage to the fish. Collaterally, a careful study of the actual values, measured during the operation, allowed adjusting the data that were used as an input to the reservoir operation.
机译:阿根廷巴塔哥尼亚Pichi Picun Leufu的项目构想很久以前,与当时的趋势一样,对环境影响的关注也很少。分流过程的第三阶段被认为是在长达18小时的时间内完全关闭河水,在此期间水库将其海拔提高10米,以使水重新流过溢洪道的波峰。在这么长的时间里,河流的水量将减少到如此严重的程度,以致对鱼类种群造成损害。通过对水库充水过程的详细研究以及对溢洪道围堰的非常精确的液压操作,可以完全控制水流,将关闭时间减少到2小时半,从而避免对鱼类造成任何损害。附带地,对作业过程中测得的实际值的仔细研究允许调整用作油藏作业输入的数据。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号