Tailing impoundment permitting, design, construction, and operation in an arctic environment

机译:在北极环境中尾矿库的许可,设计,建造和运行

获取原文
获取原文并翻译 | 示例

摘要

The Fort Knox mill, located 26 miles northeast of Fairbanks, Alaska stores an average of 41,200 tons of tailings per day in a valley fill impoundment with a capacity of approximately 200 million tons. Design, operation, and construction of the embankment incorporate considerations for arctic conditions. Unsuitable material must be removed from beneath the embankment random fill and engineered zones and grouting prevents erosion of underlying material. A comprehensive construction quality assurance program assures embankment construction meets the design specifications. The seepage collection system and interceptor wells assure the impoundment operates as a zero discharge facility. Tailings deposition methods maximize tailing density and minimize ice formation within the tailing mass. A detailed water balance is utilized to predict makeup water needs and assist in assuring emergency storage capacity requirements are maintained. Mitigation measures have been implemented to offset the acres of wetlands impacted by the tailing impoundment construction and operation.
机译:诺克斯堡工厂位于阿拉斯加费尔班克斯东北26英里处,平均每天将41,200吨尾矿存储在一个山谷填埋场中,产能约为2亿吨。路堤的设计,运营和施工考虑了北极条件。必须从路基随机填充物和工程区域下方清除不合适的材料,并且灌浆可防止侵蚀下面的材料。全面的施工质量保证计划可确保路堤施工符合设计规范。渗流收集系统和拦截井确保了水库作为零排放设施运行。尾矿沉积方法可最大程度地提高尾矿密度,并最大程度地减少尾矿中冰的形成。利用详细的水平衡来预测补充水的需求,并帮助确保维持紧急存储容量需求。已采取缓解措施,以抵消受尾矿库建设和运营影响的湿地面积。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号