ASHTABULA RIVER SEDIMENT REMEDIATION PROJECT: SLURRY TRANSPORT, DEWATERING, DISPOSAL, AND WATER TREATMENT

机译:ASHTABULA河底泥修复项目:淤泥运输,脱水,处置和水处理

获取原文
获取原文并翻译 | 示例

摘要

In September 2006, contaminated sediment dredging commenced on the Ashtabula River Remediation project under the authority of the Great Lakes Legacy Act. As part of this construction project approximately 382,000 cubic meters of contaminated sediments were hydraulically dredged from the river, transported 4.3 kilometers overland through a double-walled HDPE pipeline with three 500 Hp centrifugal booster pumps, dewatered utilizing geotextile tubes, and disposed of in a TSCA-permitted landfill specifically constructed for this project. Water from the dewatering process was treated through a 19,000 liter per minute water treatment plant, permitted by OEPA and operated under an NPDES permit. Dredging was completed on October 14, 2007. Dredging and processing operations were scheduled to take place on a 24-hours per day, 6 1/2 days per week (scheduled 1/2 day off per week for maintenance). Production during the 2006 dredging season average less than 610 cubic meters per day due to difficulties in the transport, dewatering, and water treatment systems. Upgrades to these systems during the 2006/2007 winter shutdown greatly improve production rates during the 2007 dredging season. Dredging production during the 2007 dredging season averaged over 1,760 cubic meters per day. Technical details and performance characteristics are provided regarding the transport, dewatering, disposal, and water treatment operations. Additionally, the authors discuss lessons learned during the operations that improved performance in the later stages of the project and will inform decision-making on future sites.
机译:2006年9月,在《大湖区遗产法案》的授权下,阿什塔比拉河整治项目开始了受污染的泥沙疏ed工作。作为该建设项目的一部分,从河中以液压方式疏approximately了约382,000立方米的受污染沉积物,通过带有三台500 Hp离心增压泵的双壁HDPE管道,将陆上运输了4.3公里,利用土工织物管进行了脱水,并处置在TSCA中专门为此项目建造的允许填埋场。脱水过程中的水经过OEPA许可并在NPDES许可下运行的每分钟19,000升水处理厂进行处理。疏ed工作已于2007年10月14日完成。疏Dr和加工操作计划每天24小时,每周6 1/2天(计划每周休息1/2天进行维护)进行。由于运输,脱水和水处理系统的困难,2006年疏season季节的平均日产量不到610立方米。在2006/2007年冬季停工期间对这些系统进行升级可以大大提高2007年疏dr季节的生产率。 2007年疏dr季节的疏ging产量平均每天超过1,760立方米。提供有关运输,脱水,处置和水处理操作的技术细节和性能特征。此外,作者讨论了在运营过程中获得的经验教训,这些经验教训提高了项目后期的绩效,并将为将来的选址决策提供依据。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号