ACHIEVING STRETCH TARGETS IN MINIMUM TIME

机译:在最短的时间内达到伸展目标

获取原文
获取原文并翻译 | 示例

摘要

Applying 28000kg of SS weld overlay onto 300m2 internal surface area of a tall insulated carbon steel pressure vessel within in an outage duration of 22 days sounds like a challenge. Then have three separate additional projects where "this duration is a great opportunity to do these at the same time", but they are all taking place in the same work area. Without the ability to increase the outage duration the challenge was presented to the team at Mainstream Engineering Ltd (MEL) and required some careful planning and risk management. The project had all the hazardous challenges of garnet blasting and hot work at height in a limited access confined space with multiple work fronts above and below each other. There were doubts about completing the quantity of work safely within the available time. This is not the first time MEL have been presented with this size of challenge, but it is one of the more significant. There are multiple contracting companies from different countries working 24/7, in a 500m3 volume. The presentation describes the challenges presented, the tools used and methods employed to complete the work in the time available and without incident.
机译:在22天的停机时间内,将28000kg的SS焊缝堆焊到一个高绝缘碳钢压力容器的300m2内表面上,这听起来像是一个挑战。然后有三个单独的附加项目,“这个持续时间是同时执行这些任务的绝好机会”,但是它们都在同一工作区域中进行。由于无法增加中断时间,因此挑战已提交给Mainstream Engineering Ltd(MEL)的团队,并且需要进行一些仔细的计划和风险管理。该项目在有限的通道密闭空间内进行了石榴石爆破和高空热作业的所有危险挑战,上下上下有多个工作面。对于在可用时间内安全完成工作量存在疑问。这并不是MEL首次面临如此大的挑战,但这是更为重要的挑战之一。来自不同国家/地区的多家签约公司以500立方米的体积全天候24/7工作。演示文稿描述了所提出的挑战,所使用的工具和所采用的方法,以在可用的时间内完成工作而不会发生任何事故。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号