Construction and instrumentation of waste rock test covers at Whistle Mine, Ontario, Canada

机译:加拿大安大略省惠斯勒矿山的废石测试盖的构建和仪表

获取原文
获取原文并翻译 | 示例

摘要

Inco Ltd. is currently in the process of decommissioning the Whistle Mine site located in northern Ontario, Canada. Closure of the mine site includes relocation of waste rock from two waste rock piles into an open pit, and construction of an engineered dry cover system over the potentially acid-generating waste material. The final contoured surface of the backfilled pit will have a 20% slope. Site-specific field information is required on the construction feasibility and potential performance of dry cover systems prior to finalizing the design of the full-scale cover system. Three experimental dry cover systems were constructed over acid-generating waste rock at Whistle Mine in the fall of 2000. Each test cover plot has a different barrier layer overlain by a protective layer of non-compacted soil. The three barrier layers being evaluated are a geosynthetic clay liner (GCL), a compacted sand-bentonite mixture, and a compacted local silt/trace clay material. A monitoring system was installed to evaluate field performance of the test covers, which includes continuous monitoring of climatic parameters, gaseous oxygen / carbon dioxide concentrations and moisture / temperature conditions within the cover and waste materials. The quantity of net percolation through each test cover is also being monitored. A waste rock platform with a 20% slope was constructed to support the test cover systems, as well as a seepage collection system to prevent contamination of the local groundwater system. This paper describes the construction of the test cover plots, the waste rock platform and seepage collection system, and installation of the field performance monitoring equipment.
机译:Inco Ltd.目前正在对位于加拿大安大略省北部的Whistle矿场进行退役。矿场的关闭包括将废石从两个废石堆中转移到露天矿井中,以及在可能产生酸的废料上建造工程干式覆盖系统。回填坑的最终轮廓表面将具有20%的斜率。在最终确定全尺寸覆盖系统的设计之前,需要有关现场可行性的干覆盖系统的施工可行性和潜在性能的信息。在2000年秋季,在惠斯勒矿山的产酸废石上建立了三个实验性干式覆盖系统。每个测试覆盖区都有一个不同的阻挡层,上面覆盖着一层非压实土壤。评估的三个阻隔层是土工合成粘土衬里(GCL),压实的砂-膨润土混合物和压实的局部淤泥/痕量粘土材料。安装了一个监控系统以评估测试覆盖物的现场性能,其中包括连续监测覆盖物和废料中的气候参数,气态氧/二氧化碳浓度以及湿度/温度条件。通过每个测试覆盖物的净渗滤量也受到监控。建造了一个坡度为20%的废石平台,以支撑测试覆盖系统以及一个渗漏收集系统,以防止污染当地地下水系统。本文介绍了测试覆盖区的建设,platform石平台和渗漏收集系统以及现场性能监测设备的安装。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号