首页> 外文会议>International Conference on Engineering, Project, and Product Management >A New Method to Tackle the Duration Risks of a Construction Project
【24h】

A New Method to Tackle the Duration Risks of a Construction Project

机译:一种解决建筑项目的持续时间风险的新方法

获取原文

摘要

Accurate estimation of the activity durations is the most essential element for the effective management of a construction project. Due to the complex conditions existing in the construction environment, there are many influential risk factors associated with an activity. It makes the accurate estimation of activity durations extremely difficult. The most well-known method to deal with such risks has been the Project Evaluation and Review Technique (PERT). In PERT, the different influential risk factors associated with an activity is considered simultaneously by the scheduler to come up with a set of three point estimates (i.e., most-optimistic, most-likely, and most-pessimistic) for the duration of an activity [4]. Although PERT provides a convenient approach to tackle the risks associated with activity duration, it has been criticized to be overly simplified and inaccurate. Using the three point estimates mentioned above, the expected time (t_e) for the duration of an activity can be calculated. The t_e implies the average time the task requires if the task were repeated over an extended period of time. There are several drawbacks associated with the PERT method, such as: historical records are usually not available; most schedulers are not familiar with statistic distribution; Traditional PERT provides only schedule planning but no schedule controlling method, it is difficult to control the risk factors effectively.
机译:精确估计活动持续时间是有效管理建筑项目的最重要因素。由于施工环境中存在的复杂条件,存在许多与活动相关的有影响力的危险因素。它使得精确估计活动持续时间非常困难。最着名的处理此类风险的方法一直是项目评估和审查技术(PERT)。在Pert中,调度程序同时考虑与活动相关的不同影响危险因素,以便在活动期间提出一组三点估计(即,最乐观,最乐观,最可能和最悲观的) [4]。尽管Pert提供了一种方便的方法来解决与活动持续时间相关的风险,但受到批评过度简化和不准确的批评。使用上述三点估计值,可以计算活动持续时间的预期时间(T_E)。如果在延长的时间段内重复任务,则T_E意味着任务需要的平均时间。有几个缺点与Pert方法相关,例如:历史记录通常不可用;大多数调度员不熟悉统计分布;传统的Pert仅提供时间表规划,但没有时间表控制方法,很难有效控制风险因素。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号