Time Delay and Cost Overrun in Qatari Public Construction Projects

机译:卡塔里公共建设项目的时间延迟与成本超支

获取原文

摘要

This paper investigated cost overruns and delays in Qatari public construction projects. An extensive review of regional and international publications was conducted to get a better understanding of the problem and the various methodologies that were used to analyze it. The data that was collected from Qatar public work authority ASHGHAL included 122 public road, building, and drainage projects. ANOVA method was used for data analysis and inference. A regression analysis was also conducted to establish the relationships between project contract prices and cost overruns and to develop prediction models for estimating cost overruns. Two linear regression models were developed for predicting cost overruns for building and drainage public projects, respectively. Cost overruns for building projects increased with contract prices. On the other hand, cost overruns for drainage projects decreased with increasing contract prices. A significant effort was spent in collecting data on cost overruns and delays in public construction projects. However, data confidentiality did allow the collection of enough data to ensure the robustness of the developed regression prediction models.
机译:本文调查了卡塔里公共建设项目的成本超支和延误。对区域和国际出版物进行了广泛的审查,以更好地了解问题和用于分析它的各种方法。从卡塔尔公共工程权威ashghal收集的数据包括122个公共道路,建筑和排水项目。 ANOVA方法用于数据分析和推理。还进行了回归分析,以建立项目合同价格与成本超支之间的关系,并开发用于估算成本超支的预测模型。开发了两个线性回归模型,用于预测建筑和排水公共项目的成本超支。建筑项目的成本超支增加了合同价格。另一方面,随着合同价格的增加,排水项目的成本超支减少。在收集有关成本超支和公共建设项目延误的数据中,共度努力。但是,数据机密性确实允许收集足够的数据来确保发布的回归预测模型的稳健性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号