A Research for special piers' adjustment of steel pipe pile position: A case of Penang second marine bridge

机译:钢管桩桩特殊桥墩调整研究 - 以槟城第二海洋桥为例

获取原文

摘要

The aim of this preliminary research is to study the precision of pile foundation position compared to its original designed location. Before the installation of steel pipe piles for this project, the subcontractor found that the present vessel and equipment could not fully satisfy the plan twist angle and inclination requirements as shown on the detailed design drawings. Adjustment to the twist angle was needed for individual piles in some pier locations. In connection to the pile positions after the adjustment, this research has compared the pile forced loads with that of the original layout, and found that the structural impact is very insignificant due to the change in twist angle. It is confirmed that the revised pile group layout is acceptable. The relevant detail design is still applicable and amendment is unnecessary. The recommendation of this research could be adopted for the similar huge marine structures which installed large diameter steel pipe piles.
机译:初步研究的目的是研究桩基位置的精度与其原始设计的位置相比。在安装该项目的钢管桩之前,分包商发现当前的船舶和设备无法完全满足平面扭曲角度和倾斜要求,如详细设计图纸所示。在一些码头位置中的单个桩需要调整扭转角度。在调整后的桩位置有关,该研究比较了原始布局的桩强制负荷,发现由于扭曲角度的变化,结构的影响非常微不足道。确认修订后的桩基布局是可以接受的。相关细节设计仍然适用,不需要修改。该研究的建议可以用于安装大直径钢管桩的类似巨大的海洋结构。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号