Key Construction Technology Of Fair-faced Concrete On China Qingdao Zhuoting Plaza Project

机译:中国青岛卓宁广场项目公平施工基层施工技术

获取原文

摘要

Construction technology of fair-faced concrete was successfully used in China Qingdao Zhuoting plaza project. Its No.l and No.2 dwelling houses are high-rise buildings and their posts and external walls were constructed with fair-faced concrete. As it is the highest fair-faced concrete project in China with 99.95m in height, four different concrete strength grades from C35 to C50 on different floors,370 days construction period through different four seasons in a year, the project meets a lot of problems and challenges. In this article, some innovations and key construction technologies were studied and used which make the project be successfully completed.
机译:中国青岛卓宁广场项目成功使用了公平混凝土施工技术。它的No.L和2号住宅是高层建筑,其柱子和外墙采用公平的混凝土构建。由于它是中国最高的公平面对的混凝土项目,高度99.95米,从C35到C50的四个不同的混凝土力量等级不同地板,370天施工期通过一年的不同四季,该项目遇到了很多问题和挑战。在本文中,研究并使用了一些创新和关键施工技术,使项目成功完成。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号