Influence Analysis of the Construction of Ground Building to the Underground Shield Tunnel Built Lately

机译:基于地下盾构隧道建设地面建设的影响分析

获取原文

摘要

The interval tunnel of Ningbo metro line 2 goes through the site of a car showroom project. By FEM analysis, the internal force of the tunnel is calculated under the ground upper load. From the engineering planning of the two projects, the time interval of the two projects is about six months to twelve months. When the interval tunnel begins to construct, the settlement of the foundation of the showroom is still not finished. By the analysis of consolidation rate of soil, the additional settlement of tunnel caused by the latter settlement of the showroom building is analyzed. And the safety of the tunnel is evaluated according to the analysis.
机译:宁波地铁2号线2的区间隧道通过汽车陈列室项目的网站。通过FEM分析,隧道的内部力在地面负载下计算。从两个项目的工程规划中,两个项目的时间间隔大约是六个月到十二个月。当间隔隧道开始构建时,展厅基础的结算仍未完成。通过分析土壤的整合率,分析了展厅建筑后一层沉降造成的隧道额外结算。根据分析评估隧道的安全性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号