IMPROVEMENTS CARRIED OUT AT HUELVA SMELTER IN THE 2007 GENERAL SHUTDOWN: A REVIEW

机译:在2007年韦尔瓦冶炼厂进行了改进,2007年将军关闭:审查

获取原文

摘要

The Huelva Flash Smelting Furnace was commissioned in September 1975. The Smelter and the Acid Plant were expanded in 1995 to their present capacity of 300,000 tpa new copper equivalent and one million tonnes of concentrate per year. During these years of operational experience, most of the initial practices have been reviewed, process control has drastically improved and main process equipment has been modernised. The fourth Flash Furnace campaign lasted 9 years (1995-2004) during which 8 million tonnes of concentrate were smelted. Increasing sulphur content in concentrates and new environmental requirements imply new challenges for smelters to keep production and operation costs down. This paper is an overview of the modifications and improvements carried out in the 2007 general shutdown in Smelter and Acid Plants. Also, environmental improvements carried out on Smelter gasses treatment systems are described.
机译:1975年9月,HUELVA Flash冶炼炉被委托。冶炼厂和酸性植物于1995年扩大到目前的300,000吨TPA新铜等量,每年百百万吨浓缩物。在这几年的运营经验中,大多数初始做法已经过审查,过程控制已急剧改进,主要的过程设备已经现代化。第四届闪光炉运动持续了9年(1995-2004),在此期间冶炼了800万吨浓缩物。增加浓缩物中的硫含量和新的环境要求意味着冶炼厂的新挑战,以保持生产和运营成本下降。本文概述了2007年冶炼厂和酸性植物的一般关机的修改和改进。此外,描述了对冶炼厂的环境改进进行了描述。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号