Comparative Analysis for Cost and Operational Differences Between Equivalent Cupola and Medium Frequency Furnace Melt Center Designs

机译:等效圆顶炉与中频炉熔体中心设计成本和运行差异的比较分析

获取原文

摘要

A thorough analysis of the operating cost and operational differences between a 40 ton/hr cupola and a 40 ton/hr medium frequency melt center was performed. The cupola and electric furnace design models include realistic cost inputs for charge materials, labor, refractory, maintenance and energy to accurately estimate melt center operating costs and final iron cost on a per ton basis for a 4,000 hr/yr melt operation. Melt center model design assumptions include the use of high efficiency furnace and equipment with energy recovery equipment where applicable. Capital equipment cost estimates for complete greenfield melt center installations for each system were used to determine break even points for both scenarios. Tables and graphs make comparisons for significant operating parameters and operational costs. This analysis provides useful data and information for the typical foundry by providing operating benchmarks for optimal melt center designs.
机译:进行了40吨/小时圆杯和40吨/小时频率熔体中心之间的运营成本和操作差异的彻底分析。圆屋拉和电炉设计型号包括充电材料,劳动力,耐火材料,维护和能量的现实成本输入,以准确地估计熔体中心运营成本和最终铁成本,每吨4,000小时/年熔体操作。熔体中心模型设计假设包括使用高效炉和设备,其中适用于能量回收设备。每个系统的完整绿地熔体中心安装的资本设备成本估计用于确定这两种情况的均匀点。表格和图表进行了显着的操作参数和运营成本的比较。该分析通过为最佳熔体中心设计提供操作基准,提供了典型代工厂的有用数据和信息。

著录项

  • 来源
    《Annual Casting Congress》|2002年||共15页
  • 会议地点
  • 作者

    M. Boehm;

  • 作者单位
  • 会议组织
  • 原文格式 PDF
  • 正文语种
  • 中图分类 TG24-532;
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号