FUEL INJECTION DESIGN AND PRACTICE AT UNITED STATES STEEL HAMILTON WORKS NO.5 BLAST FURNACE

机译:美国钢铁汉密尔顿的燃油喷射设计与实践5号高炉

获取原文

摘要

In early 1990s, Natural Gas (NG) was added as an injected fuel into United States Steel Canada, Hamilton Works No.5 Blast Furnace to reduce hot blast moisture injection. A state of the art turn key Pulverized Coal Injection (PCI) facility was commissioned in 1995. The Kawasaki Steel PCI Facility was built primarily to offset the production coke shortfall with the shutdown of No. 3, 4, 5 and 6 Coke Oven Batteries. This paper will focus on the continuous improvements that were made in fuel injection technology that include process control strategies, best operating practices, fuel lance design and geometry configuration and CFD modeling studies. Both merits and limitations of a combined natural gas and PCI with a multiple oxidant tuyere level system are also discussed.
机译:20世纪90年代初,天然气(NG)被加入到美国钢铁加拿大注入的燃料中,汉密尔顿工厂5号高炉工厂,以减少热爆水注射液。 1995年委托了现有技术转弯粉煤注射液(PCI)设施。川崎钢铁PCI设施主要是抵消生产焦炭短缺,随着3,4,5和6个焦炉电池的关闭。本文将专注于燃料喷射技术中制造的连续改进,包括过程控制策略,最佳操作规范,燃料吊灯设计和几何配置以及CFD建模研究。还讨论了组合天然气和PCI与多氧化氧化剂风口电平系统的既理和限制。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号