Analyzing A Drum-Buffer-Rope Scheduling System Executability Through Simulation

机译:通过仿真分析鼓缓冲绳调度系统可执行性

获取原文

摘要

This study was carried out in a plastic workshop of a refrigerator factory to solve problems of excessive work in process. In order to provide synchronous manufacturing between Capacity Constrained Resources (CCR) and non- Capacity Constraint Resources (non-CCR), an approach was developed based on the Drum-Buffer-Rope (DBR) scheduling system, which was intended for solving problems such as this. The approach was based on a heuristic that integrates Wagner-Whitin's algorithm and finite loading method to determine optimum lot sizes for non-CCR machine's material release schedule. A simulation model was used to analyze whether an improved scheduling approach was appropriate or not. An experimental study was also conducted to determine the time buffers.
机译:本研究是在冰箱工厂的塑料研讨会中进行,解决过程中过度工作的问题。为了提供容量约束资源(CCR)和非容量约束资源(非CCR)之间的同步制造,基于鼓缓冲绳(DBR)调度系统开发了一种方法,该系统是为了解决这些问题因为这。该方法是基于启发式,集成了Wagner-Whitin的算法和有限加载方法,以确定非CCR机材料释放时间表的最佳批量尺寸。使用仿真模型来分析改进的调度方法是否合适。还进行了实验研究以确定时间缓冲液。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号