Experience from many facets of a cut-and-cover tunnel construction

机译:剪切隧道施工的许多方面的经验

获取原文

摘要

A 340-meter long cut-and-cover tunnel was constructed in soft and sensitive postglacial clays and glacial sands with a high water table in a suburban area of Switzerland maintaining traffic with local detours only. The roof slab method with diaphragmwalls was used. The thickness of the diaphragm wall and the excavation sequence were adapted to the geotechnical conditions. Detailed site investigations with borehole tests (DMT), in-situ tests (CPTU) and pore pressure monitoring were carried out. Testpanels were constructed and monitored. The construction was followed by a detailed monitoring program, which included piezometers, inclinometers, settlements, and strut forces. Measurements were evaluated and corrective action taken, if necessary. Effects on neighbouring structures were limited even with the inter- and counteracting geotechnical and hydrogeological constraints.
机译:340米长的切割隧道采用柔软敏感的后螺旋粘土和冰川砂,瑞士郊区的高水位,仅维持当地绕行的交通。使用具有隔膜的屋顶板方法。隔膜壁和挖掘序列的厚度适合于岩土条件。进行了具有钻孔试验(DMT),原位试验(CPTU)和孔隙压力监测的详细的网站调查。构建和监测Testpanel。施工之后是详细的监测计划,其中包括压力计,倾角仪,定居点和支柱力。评估测量和纠正措施,如有必要。即使是邻近的岩土工程和水文地质约束,也有限对相邻结构的影响。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号