首页> 外国专利> Cut-and-cover construction of tunnel or underground garage

Cut-and-cover construction of tunnel or underground garage

机译:隧道或地下车库的明挖式建筑

摘要

The tunnel or underground garage may be constructed using a cut-and-cover method. First a row of vertical bores (2) is drilled along the line of the walls, going down well below the level of the floor. Prefab. steel and concrete columns (3) are lowered into the holes and concrete (6) is poured in to fill up the holes. The columns have reinforcing rods (5) projecting below their bottom ends.When the wall columns are finished, the roof (9) is constructed and is tied in with the reinforcement (10) at the top of the columns. Reinforced concrete (12) is inserted between the columns and the soil under the roof is excavated down to floor level.
机译:隧道或地下车库可使用割草覆盖法建造。首先,沿墙壁的线钻出一排垂直孔(2),向下垂直于地板高度以下。预制件。将钢和混凝土柱(3)放下到孔中,然后倒入混凝土(6)填充孔。立柱的底部下方伸出有加强杆(5),完成墙立柱后,建造了屋顶(9)并与立柱顶部的加强件(10)绑在一起。将钢筋混凝土(12)插入立柱之间,并将屋顶下面的土壤挖掘到地面。

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号