CASE HISTORY OF A 240 TON/DAY RESOURCE RECOVERY PROJECT: PART II The Pittsfield, Massachusetts, Resource Recovery Facility

机译:240吨/天资源恢复项目的案例历史:第二部分Pittsfield,Massachusetts,资源恢复设施

获取原文

摘要

This paper discusses the fifteen year operating history of a resource recovery project in a small city. It is the sequel to a paper published during the first year of operation of the project (Clark, L.E., 1982a). It discusses mechanical problems and solutions, availability, and the economics of a modular combustion system generating steam for sale to an adjacent paper mill. The air pollution control retrofit and performance of a wet scrubber system for acid gas control is highlighted. The experience of co-combustion of paper mill sludge is also reported. With the decision of the City to close the landfill by 1998, ash processing is under development. The goal is to prepare aggregate for beneficial use and reduce the weight of the portion requiring disposal to less than 20% of the total residue. This would reduce the weight of material requiring final disposal to less than 5% of the weight of the incoming material. The feasibility of installing a turbine generator and increasing plant capacity is under evaluation.
机译:本文讨论了一个小城市资源回收项目的十五年度经营历史。它是在项目第一年发表的一篇文章的续集(Clark,L.E.,1982A)。它讨论了机械问题和解决方案,可用性和模块化燃烧系统的经济性,发电蒸汽销售到相邻的造纸厂。突出了空气污染控制改造和湿式洗涤系统的性能。还报道了造纸厂污泥的共燃烧的经验。随着城市在1998年关闭垃圾填埋场的决定,灰分处理正在开发中。目标是准备有益用途的总体,并减少需要处理的部分的重量少于总残留物的20%。这将减少需要最终处理的材料的重量,以少于进入材料重量的5%。在评估中安装涡轮发电机和增加植物容量的可行性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号