Power quality experiences from Sweden's first MW photovoltaics park and impact on LV planning

机译:瑞典首个兆瓦光伏电站的电能质量经验及其对低压规划的影响

获取原文

摘要

The first 1 MW PV park in Sweden was installed in 2014. A concern from the grid owner perspective is how the growing number of PV installations will influence the power quality in their grids. The power quality impact from the 1 MW park was demonstrated to fall within the regulating limitations in EIFS 2013:1 for the following aspects: voltage changes, voltage harmonics, interharmonics, and voltage unbalance. However, the slow voltage variations were exceeding the Swedish industry recommendations (AMP) governing a single production source. This deviation occurred during 0.74% of the studied two-month period. To meet AMP recommendations it would have been necessary to install a separate cable intended only for the solar park itself and connected closer to the substation. Perhaps a more appropriate alternative would have been to connect the solar park on the closest 20 kV grid.
机译:瑞典第一个1 MW光伏电站于2014年安装。电网所有者的关注点是,越来越多的PV装置将如何影响其电网的电能质量。在以下方面,证明了1兆瓦电厂的电能质量影响符合EIFS 2013:1的法规限制:电压变化,电压谐波,间谐波和电压不平衡。但是,缓慢的电压变化超出了管理单一生产源的瑞典行业建议(AMP)。这种偏差发生在研究的两个月期间的0.74%。为了满足AMP的建议,有必要安装一条单独的电缆,该电缆仅用于太阳能发电场本身,并连接至更靠近变电站的位置。也许更合适的选择是将太阳能公园连接到最近的20 kV电网上。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号