NUTS, BOLTS AND HDD: A TOUGH JOB AT A TOUGH LOCATION - CROSSING THE CAPE FEAR

机译:坚果,螺栓和硬盘:在一个艰难的位置艰难的工作 - 穿过斗篷恐惧

获取原文
获取外文期刊封面目录资料

摘要

An existing 30-inch raw water line crossing the Cape Fear River was in danger of failure due to riverbed scour and in urgent need of replacement before peak seasonal demand water requirements in Summer 2009. The solution to this problem was to replace 2,415 feet of 36-inch HDPE pipe connecting it to the existing in-service line at either end. One pipe connection was located in an environmentally sensitive tidal marsh where no drilling operation, bentonite mixing, or spoil discharge was permitted. Given these constraints, from initial design in September 2008, the HDPE line was brought into service May 7, 2009 and from concept to substantial completion, the Cape Fear River HDD crossing was completed in 7 months. Due to the limited contract time and site environmental permitting constraints, the project required innovative engineering and construction approaches. Design began in mid-September 2008 and notice-to-proceed was given to the contractor mid-January 2009. Completion was scheduled May 1, 2009. The geology at the marsh exit location, soft silty alluvial peat deposits with decayed tree stumps and root masses, presented HDD mud-pressure restrictions to prevent inadvertent drill fluid release, or better known, "frac-out". A two-drill approach was used to allow drill fluid handling, spoils removal, and pipe layout from one location. State-of-the-art drill fluid handling techniques were implemented to control, and ideally eliminate, drill-mud discharge into the exit pit. Access and equipment stability in the tidal marsh, a subgrade with no engineering value, and the environmental issues associated with a fragile ecosystem, governed all aspects of design and construction. Close coordination, cooperation, and communication between all parties, owner-designer-contractor, was necessary to get the job done, on time and on budget, leaving only footprints in the marsh.
机译:穿过毛茸茸的30英寸原始水线河流恐惧河的危险因河床冲浪而导致失败,迫切需要更换2009年夏季季节性需求水需求。这个问题的解决方案是代替2,415英尺的36英尺-Inch HDPE管道在任一端将其连接到现有的服务中。一个管道连接位于环境敏感的潮汐沼泽中,允许钻孔操作,膨润土混合或弃土放电。鉴于这些限制,从2008年9月7日的初始设计,HDPE系列于2009年5月7日签订,从概念到实质性完成,开普敦恐惧河HDD交叉在7个月内完成。由于合同时间和地点环境允许的限制有限,该项目需要创新的工程和施工方法。设计始于2008年9月中旬,并向承包商向承包商进行通知,2009年5月1日完成。沼泽出口地区的地质,腐烂的树桩和根部的软粉状冲积泥炭沉积物群众,呈现HDD泥浆压力限制,以防止无意的钻孔释放,或者更好地知道“FRAC-OUT”。使用双钻种方法来允许钻井液处理,从一个位置移除和管道布局。实现最先进的钻井液处理技术以控制,理想地消除钻探泥浆进入出口坑。潮汐沼泽中的访问和设备稳定,一个没有工程价值的路基,与脆弱的生态系统相关的环境问题,管辖了设计和建筑的各个方面。在所有各方之间的密切协调,合作和沟通,所有者 - 设计师 - 承包商都是必要的,按时和预算完成工作,只留在沼泽中的占地面积。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号