Study on evaluation system and power supply scheme for large-scale and extra-high power electric arc furnace connected to the grid

机译:大型并网超大型电弧炉评估系统及供电方案研究

获取原文

摘要

This paper analyzes adverse effect of electric arc furnace impact load on grid power quality and generator operation etc., starting from operating characteristics of electric arc furnace, and proposes evaluation system, evaluation program, and treatment measures for connection of EAF to grid. Through study of factors affecting power supply scheme for large scale extra-high power electric arc furnace, it is known that the key of power supply scheme selection is voltage fluctuation and flicker caused by connection of EAF to grid and the effect on generator shafting. Using the distributed power supply scheme for the 6 extra-high power EAF in Zhangjiagang region as an instance, an improved scheme of power supply to large scale extra-high power EAF is proposed, i.e. construction of 500 kV Jinfeng Substation that will be exclusively used for EAF loads. Results of simulation show that this scheme can greatly improve public supply network power quality and reduce effect on generator shafting.
机译:从电弧炉的运行特性入手,分析了电弧炉冲击负荷对电网电能质量和发电机运行等的不利影响,提出了电弧炉与电网连接的评估体系,评估程序和处理措施。通过研究影响大型超高功率电弧炉供电方案的因素,可以知道供电方案选择的关键是电弧炉与电网的连接引起的电压波动和闪变以及对发电机轴系的影响。以张家港地区6个特大型电炉的分布式电源方案为例,提出了大型特大型电炉的供电方案的改进方案,即建设500 kV金峰变电站专用。用于电弧炉负载。仿真结果表明,该方案可以大大提高公共供电网络的电能质量,减少对发电机轴系的影响。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号