首页> 外文会议>Canadian Society for Civil Engineering annual conference >TOP-DOWN CONSTRUCTION OF THE NEW LRT OVERHEAD BRIDGE, KITCHENER, ONTARIO
【24h】

TOP-DOWN CONSTRUCTION OF THE NEW LRT OVERHEAD BRIDGE, KITCHENER, ONTARIO

机译:自上而下的建筑新的LRT架空桥,基奇纳,安大略省

获取原文

摘要

A new Light Rail Transit (LRT) system is being constructed in Waterloo Region. The first phase of construction is scheduled for completion in 2017 and will connect Conestoga Mall in the City of Waterloo and Fairview Park Mall in the City of Kitchener, a distance of 19 km. The LRT route crosses the existing Conestoga Parkway (Highway 7/8) in Kitchener-Waterloo, requiring the construction of a new structure under the busy freeway. In 2014-15, the Ministry of Transportation, Ontario (MTO) administered the construction of the new single span bridge using a unique top-down construction technique. The highway was built during the late 1960s and early 1970s and Kitchener-Waterloo was by-passed by a new four-lane freeway now known as the Conestoga Parkway. To accommodate the existing Canadian National Rail (CNR) track which crossed the then new highway alignment, the highway was built-up on 7.5 m of fill. Recently the Conestoga Parkway was widened to six lanes between Courtland Avenue and Fischer-Hallman Road and part of the construction project included the construction of the new LRT Overhead bridge to accommodate two LRT tracks below the existing highway. The LRT crossing posed three significant challenges; first being the 7.5 m embankment, second being the requirement to maintain four lanes of traffic during construction and the third being the close proximity of the existing adjacent CNR Overhead bridge which was offset 22 m from the new LRT Overhead bridge (centerline to centerline). Traditional bottom-up construction techniques were considered but not preferred due to the extensive excavation and temporary roadway protection works required to construct the new rail crossing. Since the existing CNR bridge was not designed for unbalanced lateral earth loading, significant excavation on both sides of the CNR bridge would also be required. A top-down construction approach using secant pile abutments and a reinforced cast-in-place concrete deck slab was used to create a 12 m single-span, rigid frame bridge to accommodate two LRT tracks. This concept was similar to the Hespeler Road / CPR grade separation project, constructed in 2012, by the Region of Waterloo. A critical aspect of the LRT Overhead design was to minimize the required excavation and impacts to the existing adjacent CNR bridge with less than 11 m of soil between the two structures. The new LRT bridge design considered the future excavation and replacement of the CNR bridge. In order to maintain traffic on this busy highway, the new LRT structure was constructed in two stages. The first stage included the diversion of four lanes of traffic to the north half of the existing highway platform to permit the south half of the bridge to be constructed and the CNR bridge to be rehabilitated and widened. As previously discussed, the top-down construction approach was selected because it minimizes excavation; but some staged excavation of the existing embankment, adjacent to traffic, was required. To install the secant pile abutments and retaining walls, a level platform was prepared for the drill rigs, approximately two meters below grade which was the approximate top of caisson elevation. A temporary H-pile and lagging protection system was installed between construction stages to accommodate an approximate three meter excavation. The additional one meter excavation would be required following the installation of the secant caissons for the installation of the deck false work and construction of the concrete abutment caisson cap and deck. Two parallel secant pile abutment walls and retaining walls were constructed using a combination of unreinforced concrete filler caissons and reinforced concrete king caissons. For both types of caissons, steel liners were used to temporarily support the shaft walls to prevent collapsing of the augered holes. Where loose soil was present, the steel liner was inserted during the augering of the shaft. The liner was vibrated out immediately fol
机译:一种新的轻轨(LRT)系统在滑铁卢地区被构造。建设的第一阶段预计于2017年将在滑铁卢市和锦绣商城在基奇纳市,19公里的距离连接了Conestoga购物中心。轻铁路线穿过现有科内斯托加公园大道(公路7/8)在Kitchener滑铁卢,需要一种新的结构的繁忙的高速公路下的结构。在2014-15,交通部,安大略(MTO)管理的新单跨桥采用了独特的自上而下的施工技术建设。这条公路是在60年代末70年代初建成并基奇纳 - 滑铁卢是绕过由新的四车道高速公路现在被称为科内斯托加大路。为了适应横渡然后新公路线形现有的加拿大国家铁路(CNR)的轨道,高速公路被建成补上7.5米。最近科内斯托加大路被扩大至特兰大道和费 - 霍尔曼路和建设项目的组成部分之间的六条车道包括新的轻轨高架桥的建设,以适应现有的高速公路空两个轻轨轨道。轻铁过境提出了三个显著挑战;第一个是7.5米堤,第二个是要求施工期间维持流量的四条车道和第三个是现有的相邻CNR架空桥,它从新LRT架空桥(中心线到中心线)偏移22米的紧密接近。传统的自下而上的施工技术被认为是但不是首选,由于大量挖掘和临时道路防护工程需要构建新的铁路道口。由于现有的CNR桥不是为不平衡侧向土荷载,也将被要求在CNR桥两侧显著挖掘。使用割线桩支座自上而下结构的方法和增强铸造就地混凝土楼板被用来创建一个12米单跨度,刚构桥以容纳两个LRT轨道。这个概念是类似Hespeler路/ CPR立交工程,于2012年建造,由滑铁卢地区。轻铁架空设计的一个重要方面是与所述两个结构之间的土壤小于11米最小化所需的挖掘和影响到现有的相邻CNR桥。新的轻轨桥梁设计中考虑CNR桥的未来挖掘和更换。为了保持在这个繁忙的公路交通,新型轻轨结构分两个阶段构建。第一阶段包括了交通四个车道的高速公路现有的平台,允许将建造的大桥南半部和CNR桥进行恢复并扩大在北半边的分流。如先前所讨论,选择自顶向下的施工方法,因为它最小化了挖掘;但有些上演现有路基开挖,毗邻交通,需要。要安装咬合桩桥台及挡土墙,水平平台,为钻机,低于地面约两米,那里是海拔沉箱的顶部大概准备。临时H-桩和滞后保护系统安装施工阶段之间,以适应近似3米挖掘。附加1米挖掘将需要安装的安装混凝土桥台沉箱帽和甲板的甲板假工作和建设的割线沉箱以下。两个平行的割线桩抵接壁和挡土墙用无钢筋混凝土沉箱的填料的组合构成和钢筋混凝土沉箱王。对于这两种类型的沉箱,钢衬垫,用于临时支撑轴壁以防止augered孔塌陷。其中松土存在,该钢衬垫轴的螺旋钻期间插入。将内衬振动出立即FOL

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号