首页> 外文会议>Canadian Society for Civil Engineering annual conference >TOP-DOWN CONSTRUCTION OF THE NEW LRT OVERHEAD BRIDGE, KITCHENER, ONTARIO
【24h】

TOP-DOWN CONSTRUCTION OF THE NEW LRT OVERHEAD BRIDGE, KITCHENER, ONTARIO

机译:安大略省KITCHENER的新轻轨高架桥的自顶向下建造

获取原文

摘要

A new Light Rail Transit (LRT) system is being constructed in Waterloo Region. The first phase of construction is scheduled for completion in 2017 and will connect Conestoga Mall in the City of Waterloo and Fairview Park Mall in the City of Kitchener, a distance of 19 km. The LRT route crosses the existing Conestoga Parkway (Highway 7/8) in Kitchener-Waterloo, requiring the construction of a new structure under the busy freeway. In 2014-15, the Ministry of Transportation, Ontario (MTO) administered the construction of the new single span bridge using a unique top-down construction technique. The highway was built during the late 1960s and early 1970s and Kitchener-Waterloo was by-passed by a new four-lane freeway now known as the Conestoga Parkway. To accommodate the existing Canadian National Rail (CNR) track which crossed the then new highway alignment, the highway was built-up on 7.5 m of fill. Recently the Conestoga Parkway was widened to six lanes between Courtland Avenue and Fischer-Hallman Road and part of the construction project included the construction of the new LRT Overhead bridge to accommodate two LRT tracks below the existing highway. The LRT crossing posed three significant challenges; first being the 7.5 m embankment, second being the requirement to maintain four lanes of traffic during construction and the third being the close proximity of the existing adjacent CNR Overhead bridge which was offset 22 m from the new LRT Overhead bridge (centerline to centerline). Traditional bottom-up construction techniques were considered but not preferred due to the extensive excavation and temporary roadway protection works required to construct the new rail crossing. Since the existing CNR bridge was not designed for unbalanced lateral earth loading, significant excavation on both sides of the CNR bridge would also be required. A top-down construction approach using secant pile abutments and a reinforced cast-in-place concrete deck slab was used to create a 12 m single-span, rigid frame bridge to accommodate two LRT tracks. This concept was similar to the Hespeler Road / CPR grade separation project, constructed in 2012, by the Region of Waterloo. A critical aspect of the LRT Overhead design was to minimize the required excavation and impacts to the existing adjacent CNR bridge with less than 11 m of soil between the two structures. The new LRT bridge design considered the future excavation and replacement of the CNR bridge. In order to maintain traffic on this busy highway, the new LRT structure was constructed in two stages. The first stage included the diversion of four lanes of traffic to the north half of the existing highway platform to permit the south half of the bridge to be constructed and the CNR bridge to be rehabilitated and widened. As previously discussed, the top-down construction approach was selected because it minimizes excavation; but some staged excavation of the existing embankment, adjacent to traffic, was required. To install the secant pile abutments and retaining walls, a level platform was prepared for the drill rigs, approximately two meters below grade which was the approximate top of caisson elevation. A temporary H-pile and lagging protection system was installed between construction stages to accommodate an approximate three meter excavation. The additional one meter excavation would be required following the installation of the secant caissons for the installation of the deck false work and construction of the concrete abutment caisson cap and deck. Two parallel secant pile abutment walls and retaining walls were constructed using a combination of unreinforced concrete filler caissons and reinforced concrete king caissons. For both types of caissons, steel liners were used to temporarily support the shaft walls to prevent collapsing of the augered holes. Where loose soil was present, the steel liner was inserted during the augering of the shaft. The liner was vibrated out immediately following the placement of concrete. Each hole was topped up with concrete after the liner was removed. The construction of the secant piles involved first augering 760 mm diameter filler caisson shafts to a depth of five metres below the final top of rail elevation and filling with weak (2 MPa) concrete. The total finish length of each filler caisson ranged between 10.7 m and 11.7 m. The filler caissons were spaced at 1600 mm leaving a nominal 840 mm gap between caissons. Secondly, 1200 mm diameter king caissons, also spaced at 1600 mm, were augured by drilling overlapping holes into the weak concrete filler caissons and removing the portion of soil that remained between two the adjacent filler caissons. The king caissons shafts then had a reinforcing steel cage lowered into the hole and filled with normal 30 MPa concrete. The total finish length of each king caisson ranged between 16.7 m and 17.7 m. The depth of the king caissons were determined to provide adequate vertical capacity and to control deflections and stresses in the caissons due to lateral loads. Once the concrete in the king caissons reached sufficient strength, the additional one meter +/- of excavation was completed. The top of the caisson wall was exposed to allow for the placement of formwork and cleaning of the protruding reinforcing steel. The deck formwork was supported on grade within the approximate two meter space. The concrete abutment caisson cap, deck, barrier walls, etc. were all placed using conventional construction approaches. The remaining highway elements were finalized completing the south portion of the bridge which allowed traffic to be diverted back onto the new south half of the bridge. Construction on the north stage of the bridge was completed in the following construction season, similar to the north portion. The removal of the existing embankment material, between the abutment walls, was carried out following the completion of the bridge superstructure as discussed below. One of the most significant advantages of the top-down approach is it offers the ability to open the highway to traffic prior to removing the embankment material from inside the structure. This removes many of the substructure elements from the construction critical path. Although the design was set-up to complete the excavation at the completion of both stages, the contractor opted to complete a portion following each stage. The following provides the general sequencing based on the design approach. The pre-determined staged sequence of the embankment material was designed to control the deflections and stresses in the caisson wall during construction. 1. Following the removal of deck formwork, the interior was excavated to an average of five meters below the underside of deck 2. A temporary horizontal shoring system was installed and pre-loaded between secant pile abutment walls (Figure 1) 3. The remaining 3.4 m of embankment fill was removed from the interior, approximately 2.4 m below the final top of rail elevation 4. A granular drainage layer and permanent reinforced concrete strut was constructed between the secant pile abutment walls 5. Following the curing of the concrete strut, the temporary horizontal shoring system was removed 6. Reinforced concrete facing walls were constructed on each abutment 7. Granular bedding was placed to the underside of the rail elevation in preparation for the future installation of the ballast, ties and rails. In summary, the top-down construction approach, using seacant caissons, is a feasible technique where there is a need to minimize excavation and roadway protection. The presentation will further discuss the benefits of the top-down construction approach for the LRT bridge and also discuss the design challenges and construction aspects of the project.
机译:滑铁卢地区正在建设一种新的轻轨交通(LRT)系统。一期工程计划于2017年完成,连接滑铁卢市的Conestoga购物中心和基奇纳市的Fairview Park购物中心,相距19公里。轻快铁路线穿越了基奇纳-滑铁卢的现有Conestoga大路(7/8号高速公路),需要在繁忙的高速公路下建造新的结构。在2014-15年度,安大略省交通部(MTO)使用独特的自上而下的施工技术管理了新的单跨桥的施工。高速公路始建于1960年代末和1970年代初,基奇纳-滑铁卢绕过了一条新的四车道高速公路,现称为Conestoga Parkway。为了适应现有的加拿大国家铁路(CNR)轨道,该轨道越过了当时的新高速公路,该高速公路在7.5 m的填土上建成。最近,康尼斯托加(Conestoga)大路被扩宽至考特兰大道(Courland Avenue)和菲舍尔-哈尔曼路(Fischer-Hallman Road)之间的6条车道,部分建设项目包括建造新的轻轨高架桥,以容纳现有公路下方的两条轻轨。轻轨过境带来了三个重大挑战;第一个是7.5 m的路堤,第二个是在施​​工期间必须保持四条行车线的要求,第三个是与现有相邻的CNR高架桥的距离非常近,该桥与新的LRT高架桥相距22 m(中心线到中心线)。考虑了传统的自下而上的施工技术,但由于建造新的铁路道口需要进行大量的开挖和临时性的巷道防护工作,因此并非首选。由于现有的CNR桥并非为承受不平衡的横向土方载荷而设计,因此也需要在CNR桥的两侧进行大量开挖。自上而下的施工方法使用割线桩基台和钢筋混凝土现浇甲板板来创建一个12 m的单跨刚性框架桥,以容纳两条LRT轨道。这个概念类似于滑铁卢地区在2012年建造的Hespeler Road / CPR等级分隔项目​​。 LRT高架设计的一个关键方面是,在两个结构之间的土壤少于11 m的情况下,将所需的开挖和对现有相邻CNR桥的冲击最小化。新的LRT桥梁设计考虑了CNR桥梁的未来开挖和更换。为了维持这条繁忙的高速公路上的交通,新的轻轨结构分两个阶段建造。第一阶段包括将四行车道改道至现有公路平台的北半部,以允许建造桥梁的南半部,并修复和拓宽CNR桥梁。如前所述,选择了自上而下的施工方法,因为它可以最大程度地减少挖掘工作。但是需要对邻近交通的现有路堤进行一些分阶段的开挖。为了安装割线桩基台和挡土墙,为钻机准备了一个水平平台,该水平平台大约在地平面以下两米处,这是沉箱标高的大约顶部。在施工阶段之间安装了一个临时的H桩和防结保护系统,可容纳大约三米的开挖。在安装割线沉箱之后,将需要进行额外的一米开挖,以用于安装甲板假作业以及建造混凝土基台沉箱盖和甲板。两座平行的割线桩邻接墙和挡土墙是结合使用非钢筋混凝土填充沉箱和钢筋混凝土国王沉箱来建造的。对于两种类型的沉箱,都使用钢衬来临时支撑井壁,以防止扩孔。如果存在松散的土壤,则在竖井钻进过程中插入钢衬。放置混凝土后立即将衬板振动。除去衬里后,每个孔都用混凝土补满。割线桩的施工首先将直径为760 mm的沉箱竖井进行凿孔,使其深度低于铁路标高的最终顶部以下五米,并填充弱(2 MPa)混凝土。每个填充沉箱的总精饰长度在10.7 m至11.7 m之间。填充沉箱的间距为1600 mm,沉箱之间的标称间隙为840 mm。其次,直径1200毫米的国王沉箱,间距也为1600毫米通过在薄弱的混凝土填充物沉箱中钻出重叠孔并去除残留在两个相邻的填充沉物之间的土壤部分来预示。然后,国王沉箱竖井有一个钢筋笼,该钢筋笼降入孔中并填充有普通的30 MPa混凝土。每个沉箱的总精加工长度在16.7 m至17.7 m之间。确定了国王沉箱的深度,以提供足够的垂直承载力并控制沉箱中由于侧向载荷引起的挠曲和应力。一旦国王沉箱中的混凝土达到足够的强度,额外的一米+/-开挖就完成了。沉箱壁的顶部暴露在外,以便放置模板并清洁突出的钢筋。甲板模板在大约两米的空间内得到了坡度的支撑。混凝土桥台沉箱盖,桥面,护墙等均使用常规施工方法进行放置。其余的公路元素已完成,最终完成了桥的南部分,从而使交通被转移回新的桥南部分。与北段相似,桥梁北段的施工在接下来的施工季节内完成。在桥上部结构完成后,如下所述,在桥基壁之间清除现有的路堤材料。自上而下方法的最重要优点之一是,它能够在从结构内部移除路堤材料之前打开高速公路进行通行。这从构造关键路径中删除了许多子结构元素。尽管在两个阶段均已完成设计以完成挖掘工作,但承包商选择在每个阶段之后完成一部分工作。下面提供了基于设计方法的一般排序。堤坝材料的预定分阶段顺序设计为在施工过程中控制沉箱壁中的挠度和应力。 1.拆除甲板模板后,将内部开挖至甲板底面以下平均5米。2.临时水平支撑系统已安装并预装在割线桩基台墙之间(图1)3.其余从内部移除了3.4 m的路堤填充物,距离铁路标高4的最终顶部以下约2.4 m。在割线桩基台壁5之间构建了颗粒状排水层和永久性钢筋混凝土支杆。混凝土支杆固化后,拆除了临时的水平支撑系统。6.在每个桥台上都建造了钢筋混凝土饰面墙。7.在轨道高程的下侧放置了颗粒状的垫层,以准备将来安装压载物,扎带和轨道。综上所述,使用沉箱沉箱的自上而下的施工方法是一种可行的技术,需要将挖掘和巷道保护降至最低。该演讲将进一步讨论自顶向下的施工方法对轻轨桥梁的好处,还将讨论该项目的设计挑战和施工方面。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号