Tazimina Hydroelectric Project: A Case Study in Building a Small Hydroelectic Project in Alaska

机译:塔齐米纳水电项目:在阿拉斯加建设小型水电项目的案例研究

获取原文

摘要

A water-rich state like Alaska, filled with roaring rivers, glacier-fed lakes, and coastal regions soaked by maritime climates, offers great hydroelectric potential--if considerable obstacles can be overcome. The Tazimina River Hydroelectric Project, an 824-kW run-of-river project recently constructed in southwest Alaska, illustrates the challenges and successes encountered in developing hydroelectric projects in remote Alaska. The Tazimina project faced obstacles throughout development, from the initial permitting phase through design and construction. The facility sits above a salmon-rich stretch of the Tazimina River, ocated on private lands within a national park and preserve in Alaska. The steps involved in acquiring permits for a new project in such a location took four years to complete. The facility's design also posed problems. Complex site conditons required innovative intake structure and udnerground powerhouse design. The project's remote location, cold-weather environment, and short summer season also made construction challenging.
机译:如果可以克服相当大的障碍,像阿拉斯加这样的水资源丰富的州就充满了咆哮的河流,冰川湖和被海洋气候浸润的沿海地区,具有巨大的水力发电潜力。塔兹米纳河水电项目是一个在阿拉斯加西南部最近建造的824千瓦河道过河项目,说明了在偏远的阿拉斯加开发水电项目时遇到的挑战和成功。从最初的许可阶段到设计和施工,Tazimina项目在整个开发过程中都遇到了障碍。该设施位于塔兹米纳河(Tazimina River)富含鲑鱼的河段之上,位于国家公园内的私人土地上,并位于阿拉斯加。在这样的位置获得新项目的许可证所涉及的步骤耗时四年完成。该设施的设计也带来了问题。复杂的场地条件需要创新的进气口结构和地下动力室设计。该项目的偏远地区,寒冷的天气环境和短暂的夏季也使建筑面临挑战。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号