Commissioning a world scale ammonia plant without incident: - Providing Proactive, Not Reactive Support

机译:在没有事件的情况下调试世界范围的氨植物: - 提供积极主动,而不是反应支持

获取原文
获取外文期刊封面目录资料

摘要

In 2016, as part of the Ma'aden Umm Wu'al Phosphate Project, a 3,300 mtpd ammonia plant was commissioned in Ras Al-Khair, Kingdom of Saudi-Arabia, using the thyssenkrupp Industrial Solutions (tkIS) proprietary dual pressure ammonia process. By providing proactive technical support, Johnson Matthey and tkIS were able to predict and prepare for any issues occurring, instead of having to react when issues become incidents. This paper details the procedures and principles used to ensure that catalyst related construction and hot commissioning activities were completed without error or incident. Utilizing the years of experience between Johnson Matthey, tkIS, Ma'aden Phosphate Company and main EPC contractor, DAELIM, the plant delivered first ammonia production 25 days ahead of schedule and without catalyst related safety or quality incidents.
机译:2016年,作为Ma'aden Umm武汉磷酸盐项目的一部分,使用Thyssenkrupp Industrial Solutions(TKIS)专有双重压氨氨流程,在沙特阿拉伯王国Ras Al-Khair委托了3,300毫安氨植物。通过提供主动技术支持,约翰逊Matthey和TKIS能够预测和准备任何发生的问题,而不是在问题成为事件时进行反应。本文详述了用于确保催化剂相关建筑和热调试活动的程序和原则无需错误或事件即可完成。利用约翰逊Matthey,TKIS,Ma'aden磷酸盐公司和主要EPC承包商的多年经验,该工厂提前25天提前提供了第一个氨生产,并没有催化剂相关的安全或质量事件。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号