PROJECT DELIVERY PLAN FOR SAN VICENTE DAM RAISE

机译:圣维森特大坝上升项目交付计划

获取原文

摘要

The San Diego County Water Authority (Water Authority) will be raising San Vicente Dam in San Diego County, California to increase emergency storage, and possibly carryover storage, for the region. The existing 220-foot high concrete gravity dam will be raised by as much as 117 feet using roller compacted concrete, with construction scheduled to begin in late 2008. The dam raise is part of the Water Authority's $3.4 billion Capital Improvement Program to increase water supply reliability, and will increase the usable capacity of San Vicente Reservoir by up to 152,000 acre feet. The City of San Diego (City) owns the dam and reservoir, but the Water Authority will own the increased capacity of the expanded reservoir. This paper presents a summary of the Project Delivery Plan for the dam raise and reservoir expansion. The Project Delivery Plan is a road map for implementing the project, defining the "Who, What, Where, Why, and How" for project success. The document also defines critical interactions between the project participants throughout the entire project cycle - planning, design, construction, and start-up operations. These participants include staff in all Water Authority departments, City staff, Water Authority consultants and contractors, regulatory agencies, and other project stakeholders. The Project Delivery Plan identifies critical coordination issues between the dam raise and adjacent conveyance projects that will be used to fill the reservoir as well as deliver water to both Water Authority and City customers. This Project Delivery Plan is a "living document" which will be updated periodically to capture key decisions and progress.
机译:圣地亚哥县水务局(水务局)将在加利福尼亚州圣地亚哥县的圣维森特水坝上筑坝,以增加该地区的应急存储,并可能增加结转存储。现有的220英尺高的混凝土重力坝将使用碾压混凝土来提高117英尺,建设计划于2008年年底开始。该坝的建设是水务局34亿美元的“资本改善计划”的一部分,该计划旨在增加水的供应可靠性,并将使圣维森特水库的可用容量增加152,000英亩英尺。圣地亚哥市(市)拥有大坝和水库,但水务局将拥有扩建后的水库的增加容量。本文概述了大坝和水库扩建的项目交付计划。项目交付计划是实施项目的路线图,定义了项目成功的“人员,对象,地点,原因和方式”。该文档还定义了整个项目周期(计划,设计,施工和启动操作)中项目参与者之间的关键交互。这些参与者包括水务局所有部门的工作人员,市政府工作人员,水务局顾问和承包商,监管机构以及其他项目利益相关者。该项目交付计划确定了大坝和相邻输水项目之间的关键协调问题,这些问题将用于填满水库以及向水务局和城市客户输送水。该项目交付计划是一个“活动文档”,将定期更新以捕获关键的决策和进度。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号