HIGHWAY 407 ETR - EXPRESS TOLL ROUTE INNOVATIVE DESIGN AND CONSTRUCTION DESIGN/BUILD VERSUS TRADITIONAL DESIGN/BID/BUILD

机译:HIGHWAY 407 ETR-收费公路的创新设计和施工设计/建造与传统设计/投标/建造

获取原文
获取原文并翻译 | 示例

摘要

Early in 1997, the first phase of the $1 billion, 69 km all-electronic Highway 407ETR Express Toll Route in thernGreater Toronto Area opened to traffic, just two and a half years after start of construction. The project is beingrndeveloped, designed constructed and operated and maintained through an innovative public-private partnership betweenrnthe Ontario government through the Ontario Transportation Capital Corporation (OTCC) and Canadian HighwaysrnInternational Corporation (CHIC) under the single largest public infrastructure contract in the country's history.rnPhase two is scheduled for opening before the end of 1998.rnTraditionally in Ontario the delivery approach for large highway construction projects had been to divide them intornmultiple design and construction packages and procure each package through a design/bid/construct approach. Underrnsuch a process, and with limited annual budget allocations, Highway 407 was scheduled to be delivered over a 20rnyear period.rnA new approach was required to deliver the project in a four year period and at a lower cost. With less than 30% ofrnthe design completed, design, approvals and construction had to proceed concurrently rather than "tail-to-tail" throughrntraditional methods.rnThis paper discusses the design/build approach for Highway 407 as implemented by CHIC and OTCC. Comparisonsrnare made with traditional project delivery by the Ministry of Transportation of Ontario (MTO). The primary aspectsrnreviewed include: Single Point Responsibility; Integrated Team Approach; Proactive Review Process; StagedrnDesign Delivery, Focused Contract Design/Documentation Product; and Focused Quality Assurance.
机译:1997年初,耗资10亿加元,全长69公里的全电子高速公路407ETR快速收费公路的第一期工程在大多伦多地区开业,距开工仅两年半。该项目是安大略省政府通过安大略省交通资本公司(OTCC)和加拿大高速公路国际公司(CHIC)之间的创新公私合作伙伴关系进行开发,设计,建造和运营和维护的,这是该国历史上最大的单一公共基础设施合同。其中两个计划于1998年底前开放。在安大略省,传统上,大型公路建设项目的交付方式是将它们分为多个设计和施工包,并通过设计/投标/构造方法来采购每个包。在这样的过程中,由于年度预算拨款有限,高速公路407计划在20年内交付。需要一种新方法来在四年内以较低的成本交付项目。在不到30%的设计完成的情况下,必须同时进行设计,审批和建设,而不是通过传统方法“逐尾”。本文讨论了CHIC和OTCC实施的407号公路的设计/建造方法。安大略省运输部(MTO)与传统项目交付进行了比较。审查的主要方面包括:单点责任;综合团队方法;积极的审核流程; StagedrnDesign交付,重点合同设计/文档产品;和专注的质量保证。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号