INSTALLATION OF SECANT PILE WALL IN ROCK ADJACENT TO FRAGILE BUILDING

机译:在与易碎建筑相邻的岩石中安装正割桩墙

获取原文

摘要

The construction of an ancillary structure for the new Second Avenue Subway Line in Manhattan, New York City involved a deep excavation in highly variable rock conditions adjacent to a fragile masonry building. The maximum difference between the lowest and highest rock elevations was about 30 feet, which posed a problem for the installation of secant piles that formed the supporting retaining wall for the excavation. At certain areas, the rock levels were higher than the top of the invert slab of the ancillary structure. To avoid disturbance to the adjacent fragile building, the secant piles were fully cased for drilling through the overburden soils and the rock sockets were formed using non-vibratory technique. This paper discusses the design and installation details of the secant pile wall and the contingency measures that were considered to mitigate the highly variable rock conditions. Monitoring of the adjacent fragile building showed that impact of pile installation were controlled within tolerable limits and safety of the building was not compromised.
机译:纽约市曼哈顿新第二大道地铁线的辅助结构的施工涉及在毗邻脆弱的砖石建筑的高度变化的岩石条件下进行的深挖。最低和最高岩石标高之间的最大差约为30英尺,这对安装形成挖掘用支撑挡土墙的割线桩造成了问题。在某些区域,岩石高度高于辅助结构倒置平板的顶部。为了避免对相邻的易碎建筑造成干扰,将割线桩完全装箱以覆盖上覆的土壤进行钻孔,并使用非振动技术形成了石槽。本文讨论了割线桩墙的设计和安装细节以及为缓解高度变化的岩石条件而考虑采取的应急措施。监视相邻的易碎建筑物表明,将桩安装的影响控制在允许的范围内,并且建筑物的安全性没有受到损害。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号