Last Planner Technique: A Case Study

机译:最后计划者技术:案例研究

获取原文
获取原文并翻译 | 示例

摘要

This paper presents the findings from the application of the Last Planner Technique to a project involving the construction of the Advanced Communication and Information Technology Center (ACITC) at the Virginia Tech campus. The scope of the case study was to measure the reliability of weekly work assignments. Data collected for a period of ten weeks was analyzed to produce five different Percent Plan Complete (PPC) ratios. These PPC ratios were used to compare the performance of weekly work assignments against weekly, monthly, and baseline schedules. Related information regarding the reasons for non-completion of work assignments was also collected. The paper concludes by recommending the use of weighting factors in the computation of the PPC ratios and the establishment of industry-wide benchmarks for PPC ratios.
机译:本文介绍了“最后计划者”技术在涉及弗吉尼亚理工大学校园高级通信和信息技术中心(ACITC)建设的项目中的应用结果。案例研究的范围是衡量每周工作分配的可靠性。分析了为期十周的数据,以得出五种不同的计划完成百分比(PPC)。这些PPC比率用于比较每周工作分配与每周,每月和基线时间表的绩效。还收集了有关未完成工作任务的原因的相关信息。本文最后建议在计算PPC比率时使用加权因子,并建立PPC比率的整个行业基准。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号