Some thoughts on characteristics of floats in network planning

机译:对网络规划中的浮点数的一些思考

获取原文
获取原文并翻译 | 示例

摘要

Network is to design plans by means of network analysis, which is an effective method developed to make schedule plans for large scale projects in the end of 1950s. CPM is one of the main contents in network, and float is the main part. There are nine basic concepts, including total float, front single float, back single float, front common float, back common float, front single back common float, front common back single float, double common float and double single float. The correlation among them can reflect the characteristic of floats and the relationship between activity and total duration or activity and activity and so on. From a new point of view, the paper studied correlation among nine floats on the basis of their concepts, proposed several thought-provoking issues aiming at characteristics of floats, and summed some theorems and deductions.
机译:网络是通过网络分析来设计计划的,这是一种有效的方法,可以用来为1950年代末的大型项目制定计划表。 CPM是网络的主要内容之一,而float是主要部分。有九种基本概念,包括总浮子,前单浮子,后单浮子,前公共浮子,后公共浮子,前单后浮子,前公共后浮子,双公共浮子和双单浮子。它们之间的相关性可以反映出漂浮物的特性以及活动与总持续时间或活动与活动之间的关系等。从一个新的角度出发,本文基于九个浮子的概念研究了它们之间的相关性,针对浮子的特性提出了几个发人深省的问题,并总结了一些定理和推论。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号