An erection method by simple tower instrument during upper bridge construction installation, consists of installing 8 bolt ∅ 1 1/2" — 400 and lower joint plate 24 mm bold, ∅ 50 cm on head of bridge construction pillar as hook designed tower, installing 5 locking plates from lower plate with 24 mm bold, 42 cm height as joint of premier steel pile ∅ 30 cm, 6.5 mm bold, through 8 bolts and lower joint plate on every head of bridge construction pillar, installing and locking wind fastener ∅ 15 cm through joint plate 16 mm bold and 4 bolts ∅ 3/4" to unite premier tower 3 ∅ 30 cm, 6.5 mm bold, locating axis bearings 6 cm on outer side of premier tower as supporting part to tie and tension cable to tower, locating front stays with to 70 degree to tower to put premier supporter on premier tower through bearings, locating back stays with 50 degree to tower to stabilize tower on rear tower pillar through bolt on bridge pillar, locating arc construction onto pontoon using crane, which all arc components made segmental, from segment 1 until segment 13, which loaded onto pontoon, arranged by a way so that pontoon stay stabile during installing arc construction, installing bracing at the same time with arc construction accordingly following arc construction installation, stressing cable using twin ram jack unit or multi-strand M-PV to stabilize premier supporter installation of upper bridge, featured that to unite premier tower piles, we use segmental by unite on site as necessary, and knock down easily after installing premier supporter stabilization of upper bridge portion, meanwhile tower hook, tower, bearings, cable installation, and tension, as additional device by using existent pillars so that reduce duration and cost wholly.
机译:在上层桥梁施工安装过程中,通过简单的塔式仪器进行架设的方法包括:安装8个螺栓∅1 1/2“ — 400,以及下部连接板24 mm粗体,∅50 cm作为钩形塔架安装在桥梁施工支柱的顶部,安装5下部钢板的锁定板,加粗24毫米,高42厘米,作为高级钢桩的连接点∅30厘米,粗体6.5毫米,通过8个螺栓和下部连接板固定在桥梁建筑立柱的每个头上,安装和锁定风挡∅15厘米通过连接板16毫米粗体和4个螺栓∅3/4“来连接主塔3∅30厘米,粗体6.5毫米,定位轴轴承在主塔的外侧6厘米,作为支撑部件,以将电缆系紧并拉紧塔,前撑杆与塔架成70度角,以通过轴承将总理支撑架放置在主塔架上;后撑杆与塔架成50度角,以通过后桥支柱上的螺栓将塔架稳定在后塔架支柱上;使用起重机将弧形结构定位到浮桥上,所有弧com从第1段到第13段的各段被分段,并加载到浮桥上,其布置方式使浮桥在安装弧线施工期间保持稳定,在安装弧线施工后同时安装支撑和弧线施工,并使用双闸板对电缆施加应力千斤顶单元或多股M-PV来稳定上桥的总理支架安装,其特征在于,为了团结总理塔桩,我们在必要时采用分段结合的方式,并在安装上桥部分的总理支架稳定之后轻松拆下,同时,塔钩,塔架,轴承,电缆的安装和拉紧作为使用现有支柱的附加设备,从而可以整体上减少工期并降低成本。

著录项

  • 公开/公告号WO2010092562A1

    专利类型

  • 公开/公告日2010-08-19

    原文格式PDF

  • 申请/专利权人 BAHAT BEN BRAHIM S.;

    申请/专利号WO2010ID00003

  • 发明设计人 BAHAT BEN BRAHIM S.;

    申请日2010-02-03

  • 分类号E01D1/00;E01D21/00;

  • 国家 WO

  • 入库时间 2022-08-21 18:36:39

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号