CONSTRUCTION METHOD OF CABLE-STAYED BRIDGE

机译:斜拉桥的施工方法

摘要

PROBLEM TO BE SOLVED: To provide a construction method of a cable-stayed bridge capable of installing a main digit between side span preceding the center span without building a plurality of intermediate piers at the side span even when the span length of the side span is large.SOLUTION: As illustrated in Figs. 3(A) and (B), an intermediate pier 7 is built, and a temporary support 21 is provided to the intermediate pier 7 between a main pier 5 and an end pier 6. Subsequently, a temporal diagonal member 22 is installed by extending from the intermediate pier 7 in both bridge axial directions between a PC digit 4A and the temporary support 21 by a cantilever extension method as illustrated in Figs. 3(C) and (D). Subsequently, a PC digit 4A is bridged across a side span SS while supporting the PC digit 4A with the temporal diagonal member 22 as illustrated in Figs. 3(E) and (F).SELECTED DRAWING: Figure 3
机译:要解决的问题:提供一种斜拉桥的施工方法,即使侧跨的跨距长度为,该斜拉桥也可以在中心跨度之前的侧跨之间安装主指趾,而无需在侧跨建立多个中间墩。解决方案:如图所示。如图3(A)和(B)所示,建造中间墩7,并且在主墩5和端墩6之间在中间墩7上设置临时支撑件21。随后,通过延伸设置临时的对角构件22。如图1和图2所示,通过悬臂延伸法从中间桥墩7沿PC手指4A和临时支
撑件21之间的两个桥轴向延伸。 3(C)和(D)。随后,如图5和6所示,PC手指4A跨接在侧跨SS上,同时用颞斜构件22支撑PC手指4A。 3(E)和(F)。选定的图:图3

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号