The No. 3 blast furnace of company-hia Siderurgica Nacional (CSN) was successfully blown-in on August 7,2001 after a 99-day shutdown for a major rebuild. The first iron was tapped two days later. When fully operational the daily capacity will increase from 8000 t/day to 9400t/day.The rebuild was carried out as a turnkey contract by a consortium led by VAI Industries (UK) Ltd., the UK based subsidiary of Voest-Alpine Industrieanlagenbau (VAI), in partnership with Setal, a Brazilian engineering company. At its peak over 3500 people were involved on the site.
机译:一家名为Siderurgica Nacional(CSN)的3号高炉在经过99天的大修后停工,于2001年8月7日成功吹入。两天后,第一根铁被挖掘出来。完全投入运营后,日产能将从8000吨/天增加至9400吨/天。该改造是由VAI Industries(UK)Ltd.(Voest-Alpine Industrieanlagenbau在英国的子公司)牵头的财团进行的交钥匙合同进行的。 (VAI)与巴西工程公司Setal合作。高峰期有3500多人参与该站点。