ThyssenKrupp Forder-technik to Supply Complete Coal Handling Plant

机译:蒂森克虏伯福特技术有限公司将提供完整的煤炭处理厂

获取原文
获取原文并翻译 | 示例
           

摘要

RWE Power is building a new 2 X 1,100 MW lignite-fired power plant with opti-mized plant technology (BoA) at Neurath in North Rhine-Westphalia. According to current plans, commissioning of the new plant is due to take place in late 2009.RWE Power turned to ThyssenKrupp Fordertechnik for the supply of the complete handling system to supply lignite to the steam generators. The order is worth a total of roughly EUR 31 million and includes planning, design, supply, installation and commissioning of a coal handling and preparation plant, including buildings and structural steelwork. The entire plant, with a maximum handling capacity of 3,200 tons per hour, is designed double (100 percent reserve) and can also be run in parallel operation if required.
机译:RWE Power正在北莱茵-威斯特法伦州的诺伊拉特(Neurath)建立具有优化电厂技术(BoA)的2 X 1100 MW褐煤新电厂。根据目前的计划,新工厂的调试工作将于2009年底进行。RWEPower委托蒂森克虏伯福特技术有限公司提供整套处理系统,以向蒸汽发生器供应褐煤。该订单总价值约为3,100万欧元,包括煤炭处理和选煤厂(包括建筑物和钢结构)的规划,设计,供应,安装和调试。整个工厂的最大处理能力为每小时3,200吨,设计成两倍(100%的备用量),如果需要,也可以并行运行。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号