NextEra outlines MvP delays if ruling striking Army Corps NWP 12 stands

机译:如果统治着引导陆军军团NWP 12代表,Nextera概述了MVP延迟

获取原文
获取原文并翻译 | 示例
           

摘要

NextEra Energy has warned the US Supreme Court that the 303-mile, 2 Bcf/d Mountain Valley Pipeline could face a 15-month delay in completing construction if a district court ruling is allowed to stand undermining the US Army Corps of Engineers’ nationwide permit 12, a key water crossing permit. NextEra’s friend of the court filing June 26 came as multiple oil and gas industry groups have supported the Army Corps’ effort convince US Supreme Court to grant a stay pending appeal in the 9th Circuit of the nationwide injunction by US District Court for the District of Montana.
机译:Nextera Energy已经警告美国最高法院,如果允许区域法院裁决允许在允许建造美国军队的工程师的全国范围内许可证的美国陆军兵团的国家队伍的建筑,那么303英里,2个BCF / D山谷管道可能面临15个月的延迟 12,一个关键的排水许可证。 Nextera的法院朋友申请6月26日作为多种石油和天然气行业团体支持陆军军团的努力,说服美国最高法院在美国地区法院为蒙大拿州美国地区法院禁令第9巡回援助申请 。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号