首页> 外文期刊>Cement and Concrete Research >Delayed ettringite formation in Swedish concrete railroad ties
【24h】

Delayed ettringite formation in Swedish concrete railroad ties

机译:瑞典混凝土铁路联系中钙矾石的形成延迟

获取原文
获取原文并翻译 | 示例

摘要

A petrographic examination of cracked Swedish concrete railroad ties identified delayed ettringite formation (DBF) as the damaging mechanism. This was unexpected because the concrete railroad ties were steam-cured with a maximum concrete temperature below 60 deg C.The consensus in the published literature is that DEF only occurs in concrete subjected to heat curing above 70 deg C. However, DEF is not only influenced by the curing temperature, but also by various other factors, such as cement composition (alkalis, C_3S. C_3A, SO_3, and MgO), fineness, etc. If an unfavorable combination of these parameters exists, delayed ettringite may occur at lower temperatures than 70 deg C.In this paper, the influence of various parameters on DEF is discussed with reference to the investigated concrete.
机译:瑞典混凝土铁路开裂的岩石学检查发现,延迟的钙矾石形成(DBF)是一种破坏机制。这是出乎意料的,因为混凝土铁路枕木是在最高混凝土温度低于60摄氏度的条件下进行蒸汽养护的。公开文献的共识是,仅在经过70摄氏度以上的热养护的混凝土中才会发生DEF。受固化温度的影响,还受各种其他因素的影响,例如水泥组成(碱,C_3S,C_3A,SO_3和MgO),细度等。如果这些参数存在不利的组合,则在较低的温度下可能会发生钙矾石的延迟高于70摄氏度。本文中,参考所研究的混凝土讨论了各种参数对DEF的影响。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号