CHALLENGES ENCOUNTERED DURING CONSTRUCTION AND O&M

机译:施工和运维过程中遇到的挑战

获取原文
获取原文并翻译 | 示例
   

获取外文期刊封面封底 >>

       

摘要

Besides the geology-related problems usual in underground excavation, numerous other problems like rockslides & unprecedented floods were encountered during project construction, some of which are described below. A massive rock slide of about 1.0 million cum., occurred on 8th July, 1993 on the right bank about 120 m upstream of dam axis which completely covered the proposed location of the inlet portal of the diversion tunnel and necessitated modification in the diversion arrangement. It was seen that removal of debris to approach and construct the inlet portal at its original location and level without effecting construction schedule was not possible. Therefore, studies were carried out to shift the inlet portal upstream of the original location.The length of diversion tunnel had to be increased from 410 m to 738 m.
机译:除了在地下开挖中通常遇到的与地质有关的问题外,在项目建设过程中还遇到了许多其他问题,如岩崩和空前的洪水,下面将对其中一些问题进行描述。 1993年7月8日,在坝轴上游约120 m的右岸发生了一块约100万立方米的巨大岩石滑坡,该滑坡完全覆盖了导流隧道入口的拟议位置,并需要对导流装置进行改造。可以看出,在不影响施工进度的情况下,不可能清除碎屑以接近入口处并在其原始位置和位置建造入口。因此,进行了研究以将入口门户移至原始位置的上游。导流隧道的长度必须从410 m增加到738 m。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号