首页> 外文期刊>VGB KraftwerksTechnik >Measures to reduce emissions at the Essen-Karnap refuse-fired CHP --experience gained from commissioning and two year's operation
【24h】

Measures to reduce emissions at the Essen-Karnap refuse-fired CHP --experience gained from commissioning and two year's operation

机译:减少埃森-卡纳普垃圾焚烧热电联产的排放的措施-调试和运行两年获得的经验

获取原文
获取原文并翻译 | 示例
           

摘要

In order to meet the conditions of the 17{sup}th BImSchV, downline FGDs were installed and Commissioned at the Essen-Karnap refuse-fired CHP in 1995. Both the commissioning process and the trial run revealed various layout and design defects,which have been largely remedied in the meantime. Experience gained from the first years of operation shows that various components do, in fact, meeting the guarantees given by the supplier, but nevertheless are causing problems in the operating cycle,restricted availability and therefore additional costs not anticipated. There is still need for considerable improvement. The emission values guaranteed by the supplier are certainly met, and are even lower in some instances.
机译:为了满足第17届BImSchV的条件,1995年在埃森-卡纳普垃圾焚烧热电联产电厂安装了下行烟气脱硫装置并进行了调试。调试过程和试运行均显示出各种布局和设计缺陷,在此期间已进行了大部分补救。从开始运营的第一年中获得的经验表明,各种组件确实可以满足供应商提供的保证,但是却在运行周期中造成问题,限制了可用性,因此无法预期额外的成本。仍然需要大量改进。当然可以满足供应商保证的排放值,在某些情况下甚至更低。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号