Progress Energy's Rapid Meter Deployment

机译:Progress Energy的快速电表部署

获取原文
获取原文并翻译 | 示例
       

摘要

The accelerated installation of 2.7 million succeeds with commitment and communication. ON MAY 11, 2006, VEHICLES LOADED WITH NEW SOLID-STATE ELECTRIC METERS LEFT WAREHOUSES across Florida and North Carolina, and returned with an assortment of old electromechanical meters and a record: more than 20,000 meters exchanged in a single day. That record was set by Progress Energy (Raleigh, North Carolina, U.S.) during one of the fastest deployments in North American history. When the meter project was completed, more than 2.7 million meters were installed in only 18 months.
机译:通过承诺和沟通,加速安装了270万台设备。 2006年5月11日,车辆装载了横跨佛罗里达和北卡罗来纳州的新型固态电表仓库,并返回了各种旧的机电表,并创造了记录:一天更换了超过20,000米。该记录是Progress Energy(美国北卡罗来纳州罗利)在北美历史上最快的部署之一中创造的。当水表项目完成时,仅18个月就安装了超过270万个水表。