Yme rig delay

机译:yme钻机延迟

获取原文
获取原文并翻译 | 示例
       

摘要

Delivery of a converted jack-up production unit for Repsol's Yme field off Norway has been delayed by about a year from the original schedule as downmanning due to the Covid-19 virus has hit modification work at Aker Solutions' Egersund yard.Topsides modifications for the Maersk Inspirer are now scheduled to be completed in the fourth quarter, to be followed by offshore hook-up and commissioning, with contract start-up rescheduled for December.
机译:为挪威的Repsol的YME领域的转换后的杰克制作单位交付已经延迟了大约一年从原始时间表延迟,因为Covid-19病毒因Covid-19病毒而在Aker Solutions'Egersund院子里袭击了修改工作。目前对Maersk Inspirer的修改目前计划于第四季度完成,然后是离岸联系和调试,合同启动为12月重新安排。