Handling the blockades while excavating the surge shaft at Tala Hydroelectric Project

机译:在塔拉水电项目开挖调压井时处理障碍物

获取原文
获取原文并翻译 | 示例
           

摘要

Every component in a hydel project is an important element. Delay in any one component will affect the project time and cost equally. Excavation of surge shaft is one such component which happens to be the most critical as it involves multiple stages for its completion. This operation as such is slow, difficult and if it encounters adverse geology the operation puts the entire project on the critical path. This paper discusses in detail the problems encountered during the entire excavation of a surge shaft for a 1020 MW hydel project in Himalayan geology with special reference to the blockades. It deals with the methods adopted to clear the chokes at various stages of excavation and to achieve the accelerated progress by full face blasting.
机译:hydel项目中的每个组件都是重要的元素。任何一个组件的延迟都将同样影响项目时间和成本。调压井的开挖就是其中最关键的一个,因为它涉及多个阶段来完成。这样的操作是缓慢,困难的,并且如果遇到不利的地质条件,则该操作会将整个项目置于关键路径上。本文详细讨论了喜马拉雅地质中一个1020 MW海德尔项目的调压井整个开挖过程中遇到的问题,并特别提到了封锁问题。它涉及在开挖的各个阶段清除阻塞物并通过全爆破实现加速进展的方法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号