Soil improvement works for an offshore land reclamation

机译:海上土地复垦的土壤改良工程

获取原文
获取原文并翻译 | 示例
           

摘要

The Changi East reclamation project was carried out in five phases along the foreshore of the east coast of Singapore. The water depths in the reclaimed area ranged from 5 to 15 m. The project involved hydraulic placement of 272 million m~3 of sand onto soft seabed marine clay up to 50 m thick. A linear total of 170,000 km of prefabricated vertical drains (PVDs) were installed for accelerating the consolidation process of the underlying soft marine clay. The soil improvement works covered a total area of approximately 1200 ha. In this paper, the site conditions and the soil improvement works adopted are described.
机译:樟宜东部填海工程沿新加坡东海岸的前岸分五个阶段进行。填海区的水深为5至15 m。该项目涉及将2.72亿立方米〜3的沙子水力浇注到厚达50 m的软质海底海洋粘土上。安装了总共170,000 km的线性预制垂直排水管(PVD),以加速下面的软质海洋粘土的固结过程。土壤改良工程的总面积约为1200公顷。本文描述了场地条件和采取的土壤改良工作。

著录项

  • 来源
  • 作者

    J. Chu; M. W. Bo; A. Arulrajah;

  • 作者单位

    School of Civil and Environmental Engineering, Nanyang Technological University, Singapore;

    DST Consulting Engineers Inc., Thunder Bay, Ontario, Canada;

    Swinburne University of Technology, Melbourne, Australia;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号