Extension to the Port of Tarragona breakwater, Spain

机译:西班牙塔拉戈纳防波堤的扩建

获取原文
获取原文并翻译 | 示例
           

摘要

Recent works at the Port of Tarragona in Spain invovled extending the length of the existing outer breakwater by 845 m following the same alignment. A vertical breakwater solution was adopted composed of reinforced-concrete prefabricated caissons with walls 24 m wide, 26 m wide at the base and founded at elevationrn-21.50 m. A total of 11 caissons were constructed, each 66.85 m long, the new breakwater being joined to the old one by a typical section of rubblemound breakwater with an armour layer composed of 39 t massed concrete blocks at the trunk of the breakwater and 59 t blocks at the roundhead. The depth of the seabed where the works were constructed ranges progressively from approximately 23 to 27 m. While the works were being performed, the Pineda Beach was regenerated with successive loads of sand (400 000 m~3 in 4 years), in fulfilment of the environmental impact statement for the project. It took 34 months to complete the works.
机译:西班牙塔拉戈纳港的最新工程包括,按照相同的路线,将现有外部防波堤的长度延长845 m。采用垂直防波堤解决方案,该方案由钢筋混凝土预制沉箱组成,壁厚24 m,底部宽26 m,高程rn-21.50 m。总共建造了11个沉箱,每个沉箱长66.85 m,新的防波堤通过碎石防波堤的典型部分与旧的防波堤相连,该防波堤的防波堤由防波堤后部的39吨大块混凝土砌块和59吨砌块组成。在圆头上。施工所在的海床深度逐渐从大约23到27 m不等。在进行工程的同时,Pineda海滩也进行了连续的沙子加载(4年内达到40万m〜3),以实现该项目的环境影响报告。完成这项工程花了34个月。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号