首页> 外文期刊>Practice periodical on structural design and construction >Project Management and Delay Factors of Public Housing Construction
【24h】

Project Management and Delay Factors of Public Housing Construction

机译:公共住房建设的项目管理与延迟因素

获取原文
获取原文并翻译 | 示例
           

摘要

Most reported project management studies to identify major factors in construction delay are based on self-administered questionnaire surveys of the views of project participants. A small number of studies are based on the records of actual construction projects. No study of major delay factors based on the analysis of extension of time of construction projects has been reported in the literature. A study on project management in public housing construction and delay factors based on extensions of time for 184 high-rise apartment blocks of the public housing agency in Singapore is reported herein. A comparison of major delay factors identified by this study with those identified in an earlier study is reported. Comparison is also made with studies for Hong Kong, South Korea, and Taiwan. Measures to improve the schedule performance of the development of public housing projects with respect to the delay factors identified are proposed in this paper.
机译:为确定施工延误的主要因素,大多数报告的项目管理研究都是基于对项目参与者观点的自我管理问卷调查。少数研究是基于实际建设项目的记录。尚未有文献报道基于建设项目工期延长的主要延迟因素的研究。本文报道了一项基于新加坡公共住房机构184个高层公寓楼时间延长的公共住房建设项目管理和延迟因素的研究。据报道,该研究确定的主要延迟因素与早期研究确定的主要延迟因素进行了比较。还对香港,韩国和台湾的研究进行了比较。本文提出了针对已确定的延迟因素改善公共住房项目开发进度性能的措施。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号