Exploring the impact of innovative developments to the installation process for an offshore wind farm

机译:探索创新发展对海上风电场安装过程的影响

获取原文
获取原文并翻译 | 示例
           

摘要

For offshore wind to be competitive with mature energy industries, cost efficiencies must be improved throughout the lifetime of an offshore wind farm (OWF). With expensive equipment hire spanning several years, installation is an area where large savings can potentially be made. Installation operations are subject to uncertain weather conditions, with more extreme conditions as OWF developments tend towards larger sites, further offshore in deeper waters. One approach to reduce the cost of the installation process is to evaluate advanced technologies or operational practices. However, in order to demonstrate cost savings, the impact of these advances on the installation process must be quantified in the presence of uncertain environmental conditions. To addresses this challenge a simulation tool is developed to model the logistics of the installation process and to identify the vessels and operations most sensitive to weather delays. These operations are explored to identify the impact of technological or operational advances with respect to weather delays and the resulting installation duration under different levels of weather severity. The tool identifies that loading operations contribute significantly to the overall delay of the installation process, and that a non-linear relationship exists between vessel operational limits and the duration of installation. (C) 2015 Elsevier Ltd. All rights reserved.
机译:为了使海上风能与成熟的能源行业竞争,必须在海上风电场(OWF)的整个生命周期内提高成本效率。由于昂贵的设备租赁需要花费数年的时间,因此安装是可以节省大量资金的领域。安装操作会受到不确定的天气条件的影响,随着OWF的发展趋向更大的场地,更深的海域,安装条件会更加极端。降低安装过程成本的一种方法是评估先进技术或操作实践。但是,为了证明节省了成本,必须在不确定的环境条件下量化这些进步对安装过程的影响。为了应对这一挑战,开发了一种仿真工具来对安装过程的后勤进行建模,并确定对天气延迟最敏感的船只和作业。对这些操作进行了探索,以确定技术或操作方面的进步对天气延迟的影响,以及在不同的天气严重程度下产生的安装持续时间。该工具可以识别出装载操作对安装过程的总体延迟做出了重大贡献,并且容器操作极限与安装持续时间之间存在非线性关系。 (C)2015 Elsevier Ltd.保留所有权利。

著录项

  • 来源
    《Ocean Engineering》 |2015年第15期|623-634|共12页
  • 作者单位

    Univ Strathclyde, Dept Management Sci, Glasgow G1 1QE, Lanark, Scotland|Univ Strathclyde, Dept Naval Architecture Ocean & Marine Engn, Glasgow G4 0LZ, Lanark, Scotland;

    Univ Strathclyde, Dept Management Sci, Glasgow G1 1QE, Lanark, Scotland|Univ Strathclyde, Dept Naval Architecture Ocean & Marine Engn, Glasgow G4 0LZ, Lanark, Scotland;

    Univ Strathclyde, Dept Management Sci, Glasgow G1 1QE, Lanark, Scotland;

    Univ Strathclyde, Dept Naval Architecture Ocean & Marine Engn, Glasgow G4 0LZ, Lanark, Scotland;

    Univ Strathclyde, Dept Naval Architecture Ocean & Marine Engn, Glasgow G4 0LZ, Lanark, Scotland;

    Univ Strathclyde, Dept Management Sci, Glasgow G1 1QE, Lanark, Scotland;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

    Wind energy; Offshore wind farms; Installation logistics; Discrete event simulation;

    机译:风能;海上风电场;设施物流;离散事件模拟;