【24h】

Seismic Retrofit of Tuttle Creek Dam

机译:塔特尔克里克大坝的抗震改造

获取原文
获取原文并翻译 | 示例
           

摘要

This paper discusses the seismic retrofit of Tuttle Creek Dam near Manhattan, Kansas, including investigations, seismic analyses, design, construction, and stabilization techniques used. Original plans called for stabilization of the upstream and downstream slopes and in-stallation of an upstream cutoff wall to reduce underseepage. However, constructability and dam safety issues, along with the results of refined seismic deformation analyses, led to cancellation of the jet grouted upstream slope stabilization and cutoff wall. Downstream slope stabilization was to be accomplished by jet grouting or soil mixing, but ultimately was accomplished using a self-hardening cement-bentonite (C-B) slurry to construct transverse shear walls. A total of 351 transverse shear walls were constructed along the downstream toe by primarily clamshell equip-ment. Typical shear walls are 13.7 m long, 1.2 m wide, and extend 18.9 m deep or about 6.1 m into the coarse foundation sands. The walls are spaced at 4.3 m on center along the downstream toe for a replacement ratio of about 29%. In addition to the transverse shear walls, the relief well collection ditch along the downstream toe was replaced with a buried collector system to further improve downstream stability and underseepage control.
机译:本文讨论了堪萨斯州曼哈顿附近的塔特尔克里克大坝的地震改造,包括调查,地震分析,设计,施工和所用的稳定技术。最初的计划要求稳定上游和下游坡度,并安装上游防渗墙以减少渗漏。但是,可施工性和大坝安全问题以及精细的地震变形分析结果导致取消了喷射灌浆的上游边坡稳定和防渗墙。下游边坡稳定将通过喷射灌浆或土壤混合来实现,但最终使用自硬化的水泥-膨润土(C-B)泥浆来构建横向剪力墙来实现。主要通过翻盖设备沿下游脚趾总共建造了351个横向剪力墙。典型的剪力墙长13.7 m,宽1.2 m,延伸到粗基砂中深18.9 m或约6.1 m。墙体沿下游脚趾在中央隔开4.3 m,置换率为约29%。除横向剪力墙外,沿下游脚趾的溢流井集水沟被埋藏式集水系统取代,以进一步改善下游稳定性和防渗能力。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号