Quantifying the Impact of Schedule Compression on Labor Productivity for Mechanical and Sheet Metal Contractor

机译:量化进度压缩对机械和钣金承包商的劳动生产率的影响

获取原文
获取原文并翻译 | 示例
       

摘要

In a typical construction project, a contractor may often find that the time originally allotted to perform the work has been severely reduced. The reduction of time available to complete a project is commonly known throughout the construction industry as schedule compression. Schedule compression negatively impacts labor productivity and consequently becomes a source of dispute between owners and contractors. This paper examines how schedule compression affects construction labor productivity and provides a model quantifying the impact of schedule compression on labor productivity based on data collected from 66 mechanical and 37 sheet metal projects across the United States. The model can be used in a proactive manner to reduce productivity losses by managing the factors affecting productivity under the situation of schedule compression. Another useful application of the model is its use as a litigation avoidance tool after the completion of a project.
机译:在典型的建筑项目中,承包商通常会发现原本分配给执行该工作的时间已大大减少。缩短完成项目所需的时间在整个建筑行业中通常被称为进度压缩。进度压缩会对劳动生产率产生负面影响,因此成为业主和承包商之间争执的根源。本文研究了进度压缩如何影响建筑劳动生产率,并基于从美国66个机械项目和37个钣金项目中收集的数据,提供了一个量化进度压缩对劳动生产率影响的模型。通过管理在计划压缩情况下影响生产率的因素,可以以主动方式使用该模型来减少生产率损失。该模型的另一个有用应用是在项目完成后将其用作避免诉讼的工具。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号