Quantifying the impact of schedule compression on construction labor productivity.

机译:量化进度压缩对建筑工人生产率的影响。

获取原文
获取原文并翻译 | 示例

摘要

The reduction of time available to complete a project is commonly known throughout the construction industry as schedule compression. Schedule compression is a problem because it negatively impacts labor productivity in various ways, and it becomes a source of dispute between the owners and contractors. Exacerbating the problem is the fact that schedule compression is a common occurrence on construction projects. Furthermore, the court recognizes that contractors usually fail to show a cause-effect relationship between the schedule compression and increased cost. Without demonstrating damages and being able to quantify them, the additional cost of lost productivity can not be compensated.;The objectives of this research were to investigate and quantify the impact of the three most common schedule compression methods: overtime, overmanning, and shift work on construction labor productivity, and to develop a model that quantifies the total impact of schedule compression on labor productivity at the project level.;The first objective was achieved by developing quantification models for each respective method. The second objective was achieved by introducing a quantitative definition of schedule compression that compares actual project duration to its corresponding normal duration for the same type and size of a project, and developing a logistic regression model that determines whether a project was impacted by schedule compression and a quantification model that quantifies the total impact of schedule compression on labor productivity. The application process provided in chapter six and the models developed in this study can provide guidance for contractors and owners and for resolving disputes that arise about lost productivity caused by schedule compression, and best practices provided at the end of this study will identify ways to mitigate productivity loss from schedule acceleration and compression.
机译:缩短完成项目所需的时间在整个建筑行业中通常被称为进度压缩。进度压缩是一个问题,因为它以各种方式对劳动生产率产生负面影响,并且成为业主和承包商之间争执的根源。加剧问题的是时间表压缩在建筑项目中很常见。此外,法院认识到承包商通常没有表现出时间表压缩与成本增加之间的因果关系。在没有证明损害并无法量化损害的情况下,生产力损失的额外成本无法得到补偿。本研究的目的是调查和量化三种最常见的进度压缩方法的影响:加班,超员和轮班工作关于建筑劳动生产率的研究,并建立一个量化模型,以量化进度压缩对项目水平劳动生产率的影响。;第一个目标是通过为每种方法开发量化模型来实现的。通过引入定量的进度压缩定义来实现第二个目标,该定量比较将相同项目类型和规模的实际项目工期与其对应的正常工期进行比较,并开发逻辑回归模型来确定项目是否受进度压缩和一个量化模型,用于量化进度压缩对劳动生产率的总体影响。第六章中提供的应用程序和本研究中开发的模型可以为承包商和业主以及解决因进度压缩导致的生产力损失而引起的纠纷提供指导,并且在研究结束时提供的最佳实践将确定缓解方法。进度加速和压缩会导致生产力损失。

著录项

  • 作者

    Chang, Chul-Ki.;

  • 作者单位

    The University of Wisconsin - Madison.;

  • 授予单位 The University of Wisconsin - Madison.;
  • 学科 Engineering Civil.;Sociology Industrial and Labor Relations.
  • 学位 Ph.D.
  • 年度 2004
  • 页码 177 p.
  • 总页数 177
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

  • 入库时间 2022-08-17 11:43:35

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号