Probabilistic Assessment of Cost, Time, and Revenue in a Portfolio of Projects Using Stochastic Agent-Based Simulation

机译:使用基于随机代理的模拟对项目组合中的成本,时间和收入进行概率评估

获取原文
获取原文并翻译 | 示例
           

摘要

Unforeseen conditions and uncertainties typically surround construction projects during the execution phase. These uncertainties are the main reason for schedule delays and cost overruns. Stochastic simulation models have been developed to consider projects' uncertainties and various probabilities. Although numerous studies have been conducted on causes and effects of uncertainties in individual projects, the uncertainties in a portfolio of projects have not been assessed. This study presents an agent-based simulation model developed to consider time and cost uncertainties in an owner's portfolio of projects. The model can simulate different conditions and scenarios, taking into account costs inflation during projects' execution periods. It contributes to the portfolio management body of knowledge by simulating the progress of a portfolio of projects against different scenarios, considering stochastic time, cost, and inflation rates. The simulation results assist owners to do probabilistic assessment and reduce uncertainties and risks related to time, cost, and revenue of their portfolio of projects and calculate the confidence level of their decisions and strategies. To demonstrate the capabilities of the model, an example portfolio containing 50 projects is modeled and different scenarios are evaluated. Results of the simulation indicate the model works well and provides detailed information at the portfolio level and projects' level. Fitting probability distributions to the results, it is seen that using the most likely numbers as deterministic parameters may lead to overestimating portfolio revenue and cost. The results indicate that using the portfolio stochastic agent-based simulation model can have significant effects on organizations' predictions regarding their costs and revenues.
机译:在执行阶段,施工项目通常会遇到无法预料的条件和不确定性。这些不确定性是进度延误和成本超支的主要原因。已经开发出随机模拟模型来考虑项目的不确定性和各种概率。尽管已对单个项目中不确定性的原因和影响进行了许多研究,但尚未评估项目组合中的不确定性。这项研究提出了一种基于代理的仿真模型,该模型旨在考虑所有者项目组合中的时间和成本不确定性。该模型可以模拟不同的条件和方案,并考虑项目执行期间的成本膨胀。通过考虑随机时间,成本和通货膨胀率,针对不同情况模拟项目组合的进度,它有助于组合管理知识体系。仿真结果可帮助业主进行概率评估,并减少与项目组合的时间,成本和收入相关的不确定性和风险,并计算其决策和策略的置信度。为了演示该模型的功能,对包含50个项目的示例投资组合进行了建模,并评估了不同的方案。仿真结果表明该模型运行良好,并提供了投资组合级别和项目级别的详细信息。根据结果​​拟合概率分布,可以看出,使用最可能的数字作为确定性参数可能会导致高估投资组合的收入和成本。结果表明,使用基于投资组合随机代理的仿真模型可以对组织的成本和收入预测产生重大影响。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号