Assessing the Impacts of an IT LPS Support System on Schedule Accomplishment in Construction Projects

机译:评估IT LPS支持系统对建设项目进度实现的影响

获取原文
获取原文并翻译 | 示例

摘要

This paper seeks to identify improvements in the level of implementation of the Last Planner System (LPS) with the use of information technologies (IT) based on its methodology. In addition, we correlate the level of implementation of specific LPS components to the plan percent complete (PPC). The conjoint analysis of IT benefits in implementation and correlation to PPC allowed identification of two critical components: the standardization of the planning and control process, which can be quantitatively assessed by the PPC, and the systematic analysis and removal of constraints assessed through the percentage of constraints removed (PCR). A sample of 50 projects was used to corroborate that projects that have higher PPC and PCR also have better performance, measured by the schedule accomplishment and number of noncompliances. Consequently, results inferred that projects that use IT systems based on LPS have a more systematic planning and control and better constraint management that also correspond to better schedule accomplishment and less noncompliance.
机译:本文力求通过使用信息技术(IT)的方法来确定末级计划者系统(LPS)实施水平的提高。此外,我们将特定LPS组件的实施水平与计划完成百分比(PPC)相关联。 IT收益在实施过程中的相关分析以及与PPC的相关性,可以确定两个关键组成部分:计划和控制流程的标准化,可以由PPC进行定量评估;系统地分析和消除约束,可以通过PPC的百分比进行评估。取消约束(PCR)。使用了50个项目的样本来证实,具有较高的PPC和PCR的项目也具有更好的性能,这可以通过进度完成情况和违规数量来衡量。因此,结果表明,使用基于LPS的IT系统的项目具有更系统的计划和控制以及更好的约束管理,这也对应于更好的进度完成和更少的违规情况。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号