首页> 外文期刊>International Journal of Project Management >Impact of soft logic on the probabilistic duration of construction projects
【24h】

Impact of soft logic on the probabilistic duration of construction projects

机译:软逻辑对建设项目概率持续时间的影响

获取原文
获取原文并翻译 | 示例
       

摘要

Current probabilistic scheduling models are based on a single network and assume the sequences (or links or logic) between activities to be fixed. However, some links may be changeable or soft. The presence of a soft link from one activity to another indicates that the execution of these activities has several alternative sequences. This study simulates the duration of an example project by considering uncertain activity durations and probabilistic soft links. The simulated results are compared with those obtained by the program evaluation and review technique (PERT) and three other simulation-based models. The comparisons reveal that the results generated by a simulation are close to those of PERT when the simulation incorporates soft logic. Practical lessons learned by activating soft logic also are discussed.
机译:当前的概率调度模型基于单个网络,并假定要固定的活动之间的顺序(或链接或逻辑)。但是,某些链接可能是可变的或软的。从一个活动到另一个活动的软链接的存在指示这些活动的执行具有多个替代序列。这项研究通过考虑不确定的活动持续时间和概率软链接来模拟示例项目的持续时间。将模拟结果与通过程序评估和审查技术(PERT)和其他三个基于模拟的模型获得的结果进行比较。比较结果表明,当仿真包含软逻辑时,仿真产生的结果与PERT接近。还讨论了通过激活软逻辑学到的实践经验。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号